WAC 173-175-040
Activities that require department
review, approval, acceptance, authorization, or notification. (1) Activities related to the safety of dams that require
review and approval by the department as detailed in this
chapter include:
(a) Construction of a new dam;
(b) Modification of an existing dam;
(c) Removal or abandonment of an existing dam;
(d) Construction change orders for project elements that
could have an effect on public safety.
(2) Activities related to the safety of dams that require
review and acceptance by the department as detailed in this
chapter include:
(a) Adoption of an operation and maintenance (O&M) plan;
(b) Adoption of an emergency action plan (EAP);
(c) Changes to existing operation and maintenance
procedures or to an emergency action plan that could have an
effect on public safety.
(3) Activities related to the safety of dams that require
authorization from the department before proposed actions can
proceed include:
(a) Startup of construction: For a new dam;
modifications to an existing dam; or removal or abandonment of
an existing dam.
(b) Initial controlled filling of a reservoir following
new dam construction and implementation of procedures for
normal reservoir operation.
(c) Resumption of normal reservoir operation following
dam modifications or emergency action.
(4) Activities related to the safety of dams that require
a notification to the department as detailed in this chapter
include:
(a) Change of dam ownership;
(b) Advance notice of the startup of dam construction;
(c) Declaration by the project engineer of project
completion in accordance with the department approved plans
and specifications and construction change orders;
(d) Advance notice of periodic inspection; and
(e) The occurrence of an incident at the dam.
[Statutory Authority: RCW 43.21A.064, [43.21A.]080 and86.16.061
. 92-12-055 (Order 91-17), § 173-175-040, filed
6/1/92, effective 7/2/92.]