WAC 173-175-030
Definitions. As used in this chapter:
"Acceptance" means acceptance by the department that the
proposed plan(s) will satisfactorily address issues associated
with proper operation, maintenance, inspection, or emergency
action.
"Annual exceedance probability" means the chance that a
specified magnitude of some phenomenon of interest, such as a
flood or earthquake, is equaled or exceeded during a given
year.
"Approval" means approval by the department that the
proposed design, and plans and specifications conform to
accepted engineering practice and department guidelines.
"Appurtenant works" means such structures as outlet works
and associated gates and valves; water conveyance structures
such as spillways, channels, fish ladders, tunnels, pipelines,
or penstocks; powerhouse sections; and navigation locks,
either in the dam or adjacent thereto.
"Authorization" means written acknowledgement from the
department to proceed with proposed actions.
"Construction change order" means a revision to the
department approved plans and specifications that is initiated
during construction.
"Construction permit" means the permit which authorizes
construction and that the project's plans and specifications
and construction inspection plan have been reviewed and
approved by the department.
"Construction permit process" means the sequence of
activities specified in WAC 173-175-110 inclusive, beginning
with the application for construction permit and ending with
the submission of a report summarizing construction records.
"Crest length" means the total horizontal distance
measured along the axis of the dam, at the elevation of the
top of the dam, between abutments or ends of the dam. Where
applicable, this includes the spillway, powerhouse sections,
and navigation locks, where they form a continuous part of the
impounding structure.
"Critical project element" means an element of a project
whose failure could result in the uncontrolled release of the
reservoir.
"Dam" means any artificial barrier and/or any controlling
works, together with appurtenant works that can or does
impound or divert water.
"Dam abutment" means that contact location at either end
and beneath the flanks of a dam where the artificial barrier
joins or faces against the natural earth or rock foundation
material upon which the dam is constructed.
"Dam height" means the vertical distance from the natural
bed of the stream or watercourse at the downstream toe of the
impounding barrier to the maximum storage elevation. If the
dam is not across a stream or watercourse, the height is
measured from the lowest elevation of the outside limit of the
impounding barrier to the maximum storage elevation.
"Department" means the department of ecology.
"Design step level" means an integer value between one
and eight used to designate increasingly stringent design
loadings and conditions for design of critical project
elements. Design steps have a range in annual exceedance
probability from one in five hundred at Step 1 to one in one
million at Step 8.
"Downstream hazard classification" means a rating to
describe the potential for loss of human life and/or property
damage if the dam were to fail and release the reservoir onto
downstream areas. Downstream hazard classifications of 3, 2
and 1C, 1B, 1A correspond to low, significant, and high
downstream hazard classes respectively.
"Emergency condition" means a situation where life and
property are at imminent risk and actions are needed within
minutes or hours to initiate corrective actions and/or warn
the public.
"Enlargement" means any modification of a project that
will result in an increase in normal pool height and/or dam
height.
"Exigency condition" means a situation where the dam is
significantly underdesigned according to generally accepted
engineering standards or is in a deteriorated condition and
life and property are clearly at risk. Although present
conditions do not pose an imminent threat, if adverse
conditions were to occur, the situation could quickly become
an emergency.
"FERC exempted project" means a project that is
classified as exempt by the Federal Energy Regulatory
Commission (FERC) under provisions of the Federal Power Act.
"FERC licensed project" means a project whose operation
is licensed by the Federal Energy Regulatory Commission (FERC)
under provisions of the Federal Power Act.
"Freeboard" means the vertical distance between the dam
crest elevation and some reservoir level of interest.
"Hydrograph" means a graphical representation of
discharge, stage, or other hydraulic property with respect to
time for a particular location on a watercourse.
"Impounding barrier" means the structural element of the
dam that has the primary purpose of impounding or diverting
water. It may be constructed of natural and/or man-made
materials.
"Incident" means the occurrence of any dam-related event
where problems or conditions arise which may have posed a
threat to the safety or integrity of the project or which may
have posed a threat of loss of life or which resulted in loss
of life.
"Inflow design flood (IDF)" means the reservoir inflow
flood hydrograph used for sizing the spillways and for
determining freeboard. It represents the largest flood that a
given project is designed to safely accommodate.
"Maintenance" means those tasks generally accepted as
routine in keeping the project and appurtenant works in a
serviceable condition.
"Maximum storage elevation" means the maximum attainable
water surface elevation of the reservoir pool that could occur
during extreme operating conditions. This elevation normally
corresponds to the crest elevation of the dam.
"Miscellaneous construction elements" means a variety of
construction elements or activities such as, but not limited
to: Reservoir linings; parapet walls or low berms for wave
containment; minor reconstruction of isolated portions of the
impounding barrier; internal drainage improvements; and
erosion protection.
"Modification" means any structural alteration of a dam,
its reservoir, spillway(s), outlet(s), or other appurtenant
works that could significantly influence or affect the project
safety.
"Normal pool height" means the vertical distance between
the lowest point of the upstream toe of the impounding barrier
and the normal storage elevation.
"Normal storage elevation" means the maximum elevation to
which the reservoir may rise under normal operating
conditions. Where the principal spillway is ungated, the
normal storage elevation is usually established by the
elevation of the spillway crest.
"100-year flood plain" means the area inundated during
the passage of a flood with a peak discharge having a one
percent chance of being equaled or exceeded in any given year
at a specified location on a watercourse.
"Outlet" means a conduit and/or channel structure for the
controlled release of the contents normally impounded by a dam
and reservoir.
"Owner" means the person holding lawful title to the dam
or any person who owns or proposes to construct a dam.
"Periodic inspection" means a detailed inspection of the
dam and appurtenant works conducted on regular intervals and
includes, as necessary, associated engineering analyses to
confirm the continued safe operation of the project.
"Person" means any individual, firm, association, county,
public or municipal or private corporation, agency, or other
entity whatsoever.
"Plans and specifications" means the detailed engineering
drawings and specifications used to describe the layout,
materials, construction methods, etc., for assembling a
project or project element. These do not include shop
drawings or other drawings prepared by the construction
contractor for temporary construction support systems.
"Population at risk" means the number of people who may
be present in areas downstream of a dam and could be in danger
in the event of a dam failure.
"Project" means a dam and its reservoir either proposed
or existing.
"Project engineer" means a professional engineer licensed
in Washington, having direct supervision, as defined in WAC 196-24-095, in managing the engineering aspects of the project
as representative of the owner.
"Reservoir" means any basin that contains or will contain
the water impounded by a dam.
"Reservoir routing" means the procedures used to
determine the attenuating effect of reservoir storage on a
flood as it passes through a reservoir.
"Rule curve" means the rules and procedures used to
regulate reservoir levels and project operation for various
reservoir inflows and for both normal and unusual seasonal
conditions.
"Significant enlargement" means any modification of an
existing dam that results in the dam height or normal pool
height being increased by an amount greater than 5.0 feet, and
which also represents a ten percent or greater increase in dam
height or normal pool height over that which existed prior to
the modification.
"Spillway" means a channel structure and/or conduit for
the safe release of water or floodwater.
"Stop work order" means an administrative order issued to
temporarily halt construction work until a problem can be
resolved.
"Substantially complete" means that a plan, action, or
project element requires only minor additions to be complete,
and in its present state will perform the necessary functions
for its intended use.
"Surficial inspection" means a visual inspection
conducted to identify obvious defects or changed conditions.
[Statutory Authority: RCW 43.21A.064, 43.21A.080, 86.16.061,
90.03.350 and [90.03].470. 04-16-122 (Order 03-08), §
173-175-030, filed 8/4/04, effective 9/4/04. Statutory
Authority: 1995 c 8. 95-22-030 (Order 94-15), § 173-175-030,
filed 10/24/95, effective 11/24/95. Statutory Authority: RCW 43.21A.064, [43.21A].080 and 86.16.061. 93-01-090 (Order
92-35), § 173-175-030, filed 12/16/92, effective 1/16/93;
92-12-055 (Order 91-17), § 173-175-030, filed 6/1/92,
effective 7/2/92.]