WAC 173-157-110
What types of information will I need to
provide as part of my application? Your application for an
ASR project must contain, at a minimum:
(1) A description (conceptual model) of the hydrogeologic
system (see WAC 173-157-120) prepared by a hydrogeologist
licensed in the state of Washington.
(2) A project operation plan (see WAC 173-157-130) with a
description of the pilot and operational phases of the ASR
project prepared by an engineer or geologist licensed in the
state of Washington.
(3) A description of the legal framework (see WAC 173-157-140) for the proposed project.
(4) An environmental assessment and analysis (see WAC 173-157-150) of any potential adverse conditions or potential
impacts to the surrounding ecosystem(s) that might result from
the project, along with a plan to mitigate such conditions or
impacts.
The environmental assessment will establish whether a
determination of nonsignificance or an environmental impact
statement is required per SEPA regulations.
(5) A project mitigation plan (see WAC 173-157-160), if
required.
(6) A project monitoring plan (see WAC 173-157-170).
[Statutory Authority: RCW 90.03.370 (2)(b) and 90.44.460. 03-03-081 (Order 02-06), § 173-157-110, filed 1/15/03,