(1) Activities see water pollution control activities.
(2) Applicant means a public body that has applied for
funding.
(3) Best management practices (BMP) means physical,
structural, and/or managerial practices approved by the
department that prevent or reduce pollutant discharges.
(4) Cash match means moneys used to match the state share
of a grant.
(5) Ceiling amount means the highest level of financial
assistance the department can provide to a recipient for an
individual project.
(6) Centennial means the centennial clean water program.
(7) Commercial, industrial, and institutional flows mean
the portion of the total flows to a facility that originate
from large commercial establishments, industrial facilities,
or institutional sources such as state schools, hospitals, and
prisons.
(8) Competitive funding means moneys available for
projects through a statewide evaluation process.
(9) Completion date or expiration date means the date
indicated in the funding agreement in which all milestones and
objectives associated with the goals of the project are met.
(10) Concentrated animal feeding operation (CAFO) means:
(a) An animal livestock feeding operation that discharges
animal waste to the waters of Washington state more frequently
than the twenty-five-year, twenty-four-hour storm event; or
(b) An operation that is under a department
administrative order, notice of violation, a National
Pollution Discharge Elimination System permit; or
(c) An operation that will be required to have a National
Pollution Discharge Elimination System permit coverage in the
near future; or
(d) An operation designated by the Environmental
Protection Agency as polluting the waters of Washington state.
(11) Conservation easement means a recorded legal
agreement between a landowner and a public body to allow or
restrict certain activities and uses that may take place on
his or her property.
(12) Conservation plan means a document that outlines how
a project site will be managed using best management practices
to avoid potential negative environmental impacts.
(13) Construction means to erect, install, expand, or
improve water pollution control facilities or activities.
Construction includes construction phase engineering and
preparation of the operation and maintenance manual.
(14) Cost-effective alternative means the option selected
in an approved facilities plan that meets the requirements of
the project, recognizes environmental and other nonmonetary
impacts, and offers the lowest cost over the life of the
project (i.e., lowest present worth or equivalent annual
value).
(15) Department means the Washington state department of
ecology.
(16) Design means the preparation of the plans and
specifications used for construction of water pollution
control facilities or activities.
(17) Director means the director of the Washington state
department of ecology or his or her authorized designee.
(18) Draft offer and applicant list means a catalog of
all applications for financial assistance considered and those
proposed for funding, based on estimates of state and federal
budgets.
(19) Easement means a recorded legal agreement between a
public body and a landowner that allows the public body to
have access to the landowner's property at any time to
inspect, maintain, or repair loan-or-grant-funded activities
or facilities.
(20) Effective date means the date the loan or grant
agreement is signed by the department's water quality program
manager.
(21) Eligible cost means the portion of a facilities or
activities project that can be funded based on program
eligibility as defined in WAC 173-98-100 and in the most
recently updated edition of the Water Quality Financial
Assistance Guidelines (publication #10-10-049).
(22) Enforcement order means an administrative
requirement issued by the department under the authority of
RCW 90.48.120 that directs a public body to complete a
specified course of action within an explicit period to
achieve compliance with the provisions of chapter 90.48 RCW.
(23) Engineering report means a document that includes an
evaluation of engineering and other alternatives that meet the
requirements in chapter 173-240 WAC, Submission of plans and
reports for construction of wastewater facilities.
(24) Environmental degradation means the reduced capacity
of the environment to meet social and ecological objectives
and needs.
(25) Environmental emergency means a problem that a
public body and the department agree poses a serious,
immediate threat to the environment or to the health or safety
of a community and requires immediate corrective action.
(26) Equivalent residential unit (ERU) means a unit of
measurement used to express the average sewage loading
discharged from a typical full-time single-family dwelling
unit.
(27) Estimated construction cost means the expected
amount for labor, materials, equipment, and other related work
necessary to construct the proposed project.
(28) Existing need means water pollution control
facility's capacity reserved for all users, at the time of
application.
(29) Existing residential need means that portion of a
water pollution control facility's capacity reserved for
residential structures that:
(a) Exists within the project service area at the time of
application;
(b) Is connected to the facility or is scheduled to be
connected to the facility in an approved engineering report;
and
(c) Will bear the financial burden of paying for the new
facility.
(30) Extended grant payments means cash disbursements for
eligible project costs made with equal annual payments as
established in RCW 70.146.075.
(31) Facilities see water pollution control facility.
(32) Facilities plan means an engineering report that
includes all the elements required by the state environmental
review process (SERP), National Environmental Policy Act
(NEPA) as appropriate, other federal statutes, and planning
requirements under chapter 173-240 WAC.
(33) Final offer and applicant list means a catalog of
all applications for financial assistance considered and those
offered funding, based on adopted state and federal budgets.
(34) Force account means loan or grant project work
performed using labor, materials, or equipment of a public
body.
(35) Funding cycle means the events related to the
competitive process used to allocate moneys from the water
pollution control revolving fund, centennial clean water
program, and the Clean Water Act section 319 nonpoint source
program for a state fiscal year.
(36) Grant agreement means a contractual arrangement
between a public body and the department.
(37) Growth means the portion of the flows to a facility
reserved for future residential, commercial, industrial, or
institutional flows.
(38) Indirect cost means costs that benefit more than one
activity of the recipient and not directly assigned to a
particular project objective.
(39) In-kind contributions means the value of noncash
contributions provided for a project.
(40) Interlocal agreement means a written arrangement
between a grant recipient and another public body to provide
eligible grant match contributions to a project. Interlocal
agreements are subject to chapter 39.34 RCW, Interlocal
Cooperation Act.
(41) Interlocal costs means the value of goods or
services provided to a project by a public body under the
terms of an interlocal agreement. Interlocal contributions
satisfy cash matching requirements.
(42) Infiltration and inflow means water, other than
wastewater, that enters a sewer system.
(43) Infiltration and inflow correction means the
cost-effective alternative or alternatives identified in an
approved facilities plan or engineering report for eliminating
or reducing the infiltration and inflow to an existing sewer
system.
(44) Landowner agreement means a written arrangement
between a public body and a landowner that allows the public
body to have access to the property to inspect project-related
components.
(45) Loan agreement means a contractual arrangement
between a public body and the department that involves a
disbursement of moneys that must be repaid.
(46) Loan default means failure to make a loan repayment
to the department within sixty days after the payment was due.
(47) Match means the recipient share of eligible project
costs.
(48) Nonpoint source water pollution means pollution that
enters any waters from widespread water-based or land-use
activities. Nonpoint source water pollution includes, but is
not limited to atmospheric deposition; surface water runoff
from agricultural lands, urban areas, and forest lands;
subsurface or underground sources; and discharges from boats
or other marine vessels.
(49) Plans and specifications means the construction
contract documents and supporting engineering documents
prepared in sufficient detail to allow contractors to bid on
and construct water pollution control facilities. "Plans and
specifications" and "design" may be used interchangeably.
(50) Preliminary project priority list means a catalog of
all applications for financial assistance considered for
funding and submitted to the Washington state legislature for
its consideration during budget development.
(51) Project means a water quality improvement effort
funded with a grant or loan.
(52) Project completion or expiration means the date
indicated in the funding agreement in which all milestones and
objectives associated with the goals are met.
(53) Public body means a state of Washington county, city
or town, conservation district, other political subdivision,
municipal corporation, quasi-municipal corporation, those
Indian tribes recognized by the federal government, or
institutions of higher education when the proposed project is
not part of the school's statutory responsibility.
(54) Public health emergency means a situation declared
by the Washington state department of health in which illness
or exposure known to cause illness is occurring or is
imminent.
(55) Recipient means a public body that has an effective
loan or grant agreement with the department.
(56) Residential means the portion of the total flows to
a facility that originates from single family houses,
apartments, mobile home parks, small commercial facilities,
and community facilities such as local K-12 public schools,
libraries, and fire stations.
(57) Revolving fund means Washington state's water
pollution control revolving fund.
(58) Riparian buffer or zone means a swath of vegetation
along a channel bank that provides protection from the erosive
forces of water along the channel margins and external
nonpoint sources of pollution.
(59) Scope of work means a detailed description of
project tasks, milestones, and measurable objectives.
(60) Service area population means the number of people
served in the area of the project.
(61) Severe public health hazard means a situation
declared by the Washington state department of health in which
the potential for illness exists, but illness is not occurring
or imminent.
(62) Sewer means the pipe and related pump stations
located on public property or on public rights of way and
easements that convey wastewater from buildings.
(63) Side sewer means a sanitary sewer service extension
from the point five feet outside the building foundation to
the publicly owned collection sewer.
(64) State environmental review process (SERP) means the
National Environmental Policy Act (NEPA)-like environmental
review process adopted to comply with the requirements of the
Environmental Protection Agency's Code of Regulations (40 CFR
§ 35.3140). SERP combines the State Environmental Policy Act
(SEPA) review with additional elements to comply with federal
requirements.
(65) Total eligible project cost means the sum of all
expenses associated with a water quality project that are
eligible for funding.
(66) Total project cost means the sum of all expenses
associated with a water quality project.
(67) Water pollution means contamination or other
alteration of the physical, chemical, or biological properties
of any waters of the state, including change in temperature,
taste, color, turbidity, or odor; or any discharge of a
liquid, gas, solid, radioactive substance, or other substance
into any waters of the state that creates a nuisance or
renders the waters harmful, detrimental, or injurious to the
public, to beneficial uses, or to livestock, wild animals,
birds, fish, or other aquatic life.
(68) Water pollution control activities or activities
means actions taken by a public body for the following
purposes:
(a) To prevent or mitigate pollution of underground
water;
(b) To control nonpoint sources of water pollution;
(c) To restore the water quality of freshwater lakes; and
(d) To maintain or improve water quality through the use
of water pollution control facilities or other means.
(69) Water pollution control facility or facilities means
any facilities or systems for the control, collection,
storage, treatment, disposal, or recycling of wastewater,
including, but not limited to, sanitary sewage, storm water,
residential, commercial, industrial, and agricultural wastes. Facilities include all necessary equipment, utilities,
structures, real property, and interests in and improvements
on real property.
(70) Water resource inventory area (WRIA) means one of
the watersheds in the state of Washington, each composed of
the drainage areas of a stream or streams, as established in
the Water Resources Management Act of 1971 (chapter 173-500
WAC).
[Statutory Authority: Chapter 90.50A RCW, RCW 90.48.035, and 43.21A.080. 11-20-036 (Order 10-14), § 173-95A-020, filed
9/27/11, effective 10/28/11. Statutory Authority: RCW 90.48.035. 07-14-096 (Order 05-16), § 173-95A-020, filed
6/29/07, effective 7/30/07. Statutory Authority: Chapter 70.146 RCW. 01-01-042 (Order 00-10), § 173-95A-020, filed
12/8/00, effective 1/8/01. Statutory Authority: RCW 70.146.070 and 36.70A.040. 97-24-096 (Order 97-31), §
173-95A-020, filed 12/3/97, effective 1/3/98.]