WAC 136-170-030
Terms of CRAB/county contract. (1) For
projects for which RATA funds are allocated before July 1,
1995, the CRAB/county contract shall include, but not be
limited to, the following provisions:
(a) The contract shall be valid and binding (and the
county shall be entitled to receive RATA funds) only if such
contract is signed and returned to the county road
administration board within forty-five calendar days of its
mailing by the county road administration board.
(b) The county certifies that it is in compliance with
the provisions of chapter 136-150 WAC.
(c) The project will be constructed in accordance with
the scope, design and project limits as described in the final
prospectus and in accordance with the plans and specifications
approved by the county engineer.
(d) The county will notify the county road administration
board when a construction contract has been awarded and/or
when construction has commenced, and when the project has been
completed.
(e) The county road administration board will reimburse
counties on the basis of monthly progress payment vouchers
received and approved on individual projects in the order in
which they are received in the county road administration
board office, subject to the availability of RATA funds
apportioned to the region or subject to a minimum regional
balance determined by the CRABoard for the purposes of cash
flow; provided however, that if insufficient RATA funds are
available or the legislature fails to appropriate sufficient
RATA funds, payment of vouchers may be delayed or denied.
(f) The county will reimburse the RATA in the event a
project postaudit reveals ineligible expenditure of RATA
funds.
(2) For projects for which RATA funds are allocated on or
after July 1, 1995, the CRAB/county contract shall include,
but not be limited to, the following provisions:
(a) The contract shall be valid and binding, and the
county shall be entitled to receive RATA funding in accordance
with the vouchering/payment process as described in chapter 136-180 WAC, only if the contract is properly signed and
returned to the county road administration board within
forty-five calendar days of its mailing by the county road
administration board.
(b) The county certifies that it is in compliance with
the provisions of chapter 136-150 WAC.
(c) The project will be constructed in accordance with
the scope, design and project limits as described in the final
prospectus and in accordance with the plans and specifications
approved by the county engineer, and, if applicable, the
phased construction plan submitted by the county engineer to
the county road administration board.
(d) The county will notify the county road administration
board:
(i) If a single construction contract is intended to
fully complete the project, at the time of project
advertisement, construction contract, and when the project has
been completed. Should the small works roster process be
utilized, then the initial notice must occur prior to
initiating the contractor selection process.
(ii) If county forces are utilized to fully complete the
project, at the time of project notice, as required in RCW 36.77.070, commencement of construction activities, and when
the project has been completed.
(iii) If the project applies a phased construction
methodology, at those times described in a phased construction
plan, consistent with subsection (3) of this section.
(e) The county road administration board will reimburse
counties on the basis of monthly progress payment vouchers
received and approved on individual projects in the order in
which they are received in the county road administration
board office, subject to the availability of RATA funds
apportioned to the region; or subject to a minimum regional
balance determined by the CRABoard for the purposes of cash
flow; provided however, that if insufficient RATA funds are
available or the legislature fails to appropriate sufficient
RATA funds, payment of vouchers may be delayed or denied.
Counties are ineligible to receive RATA funded construction
cost reimbursements prior to satisfaction of the initial
project notice requirement described in subsection (2)(d) of
this section.
(f) The county will reimburse the RATA in the event a
project postaudit reveals ineligible expenditures of RATA
funds.
(g) The county may be required to reimburse the RATA in
the event of early termination in accordance with the
provisions of chapter 136-167 WAC.
(h) The county agrees to amend the contract in cases
where:
(i) Additional RATA funds have been requested and
approved under chapter 136-165 WAC;
(ii) Other relief from the original scope, design or
project limits has been approved by the county road
administration board under chapter 136-165 WAC; or
(iii) A project has been terminated without full RATA
reimbursement under WAC 136-167-030(2).
(i) The county agrees to provide periodic project
development progress reports as requested by the county road
administration board.
(3) Counties may implement a phased construction
methodology in the completion of RATA funded projects. A
phased construction methodology is described as the process to
implement multiple construction contracts through competitive
bid and award, contracts awarded through exercise of the small
works roster process, or construction by county forces, or a
combination of two or more of these three methods, in order to
complete a single RATA funded project. If a county elects to
use phased construction methodology, construction of at least
one of the project phases must commence by the lapsing date
and all remaining phases must commence within two years of
commencement of the first phase. In the event the county
fails to meet either of these timelines, repayment of expended
RATA funds for all phases of the project will be required
unless waived by the county road administration board in
keeping with the provisions of this section.
(a) In order to be considered phased construction, each
phase must:
(i) Be distinct, independent, and nonoverlapping
construction activities as to location and type of work;
(ii) Result in separate function and utility;
(iii) Be part of related and sequential construction
activities that lead to overall project completion;
(iv) Separately and collectively comply with state laws
as to procurement of contract work and use of county forces;
and
(v) Not be implemented in a way that would otherwise be
considered a split project, as described in WAC 136-170-060,
without first obtaining approval as a split project.
(b) In order to satisfy notification requirement of
subsection (2)(d) of this section, a phased construction plan
must be developed and submitted to the county road
administration board at least fifteen calendar days prior to
contract bid advertisement, beginning the selection process
for a contractor through a small works roster process, or
commencement of construction by county forces, whichever
occurs first. The phased construction plan must:
(i) Include a description of each construction phase, the
contracting method to be employed or that county forces will
be used;
(ii) Include an estimated cost and begin and end dates
for each construction phase; and
(iii) Describe the relationship between construction
phases and ultimate completion of the overall project.
[Statutory Authority: Chapter 36.78 RCW. 11-05-005, §
136-170-030, filed 2/3/11, effective 3/6/11. Statutory
Authority: Chapter 36.79 RCW. 01-05-008, § 136-170-030,
filed 2/8/01, effective 3/11/01; 99-01-021, § 136-170-030,
filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, § 136-170-030, filed
8/12/96, effective 9/12/96. Statutory Authority: RCW 36.79.060. 94-16-112, § 136-170-030, filed 8/2/94, effective
9/2/94. Statutory Authority: Chapter 36.78 RCW. 84-16-065
(Order 56), § 136-170-030, filed 7/30/84.]