WAC 136-163-050
Limitations and conditions -- Emergency and
emergent projects. All projects for which RATA funding is being
requested under this chapter are subject to the following:
(1) The requesting county has the sole burden of making a
clear and conclusive showing that the project is either emergent
or emergency as described in WAC 136-163-020 through 136-163-040;
(2) The requesting county shall clearly demonstrate that the
need for the project was unable to be anticipated at the time the
current six-year transportation program was developed; and
(3) The requesting county agrees to a reduction in the next
funding period's maximum RATA eligibility to the county equal to
the RATA that may be provided; however, should that region not
have a maximum RATA eligibility for each county, the requesting
county agrees to withdraw, amend or delay an existing approved
project or portion thereof in an amount equal to the RATA that
may be provided for the project.
[Statutory Authority: Chapter 36.79 RCW. 01-05-009, §
136-163-050, filed 2/8/01, effective 3/11/01; 99-01-021, §
136-163-050, filed 12/7/98, effective 1/7/99. Statutory
Authority: RCW 36.79.060. 96-17-014, § 136-163-050, filed
8/12/96, effective 9/12/96.]