WAC 136-161-070
RAP program cycle -- Selection and
approval of projects for RATA funding. (1) At its last
regular meeting before the beginning of each biennium, the
county road administration board will select projects and
allocate anticipated RATA funds to projects in each region. The preliminary priority arrays as developed in WAC 136-161-060 will be updated to exclude any county which is
ineligible under chapter 136-150 WAC, and projects will be
selected from these arrays. Selections will be made in each
region in declining priority rank order, provided that:
(a) No county shall be allocated RATA funds in excess of
its regional county limit as specified in WAC 136-161-080; and
(b) Any projects which were partially funded in the prior
biennium shall, unless otherwise requested by the county, be
fully funded before new projects are selected. Ties in total
rating points will be broken by the county road administration
board in favor of the county having the lesser total amount of
previously allocated RATA funds.
(2) The statewide net amount of RATA funds available for
allocation to projects in the funding period will be based on
the most recent state fuel tax revenue forecast prepared
quarterly by the department of transportation, less estimated
administrative costs, and less any amounts set aside for
emergent projects as described in WAC 136-163-020. The total
amount of RATA funds available for allocation to projects in a
region (i.e., "forecasted regional apportionment amount") will
be based on the regional apportionment percentages of the
statewide net amount as determined in chapter 136-100 WAC.
(3) Project program periods and the corresponding funding
periods shall both begin on July 1st of odd numbered years and
end on June 30th of odd numbered years, unless modified by
resolution of the board.
(4) The RATA amounts allocated to projects in the first
year of the biennium are limited to no more than ninety
percent of the net amount estimated to be allocable to each
region for the project program period, with the remaining
percentage allocated at such time as deemed appropriate by the
county road administration board.
(5) Acceptance of the RATA allocation for a project by
the full execution of a CRAB/county contract as described in
chapter 136-170 WAC constitutes agreement to complete the
project in compliance with the scope, design and project
limits in the final prospectus. All material changes to the
scope, design or project limits must be approved by the county
road administration board prior to commencement of
construction.
[Statutory Authority: Chapter 36.78 RCW. 11-05-005, §
136-161-070, filed 2/3/11, effective 3/6/11. Statutory
Authority: Chapter 36.79 RCW. 01-05-009, § 136-161-070,
filed 2/8/01, effective 3/11/01; 99-01-021, § 136-161-070,
filed 12/7/98, effective 1/7/99; 98-09-070, § 136-161-070,
filed 4/20/98, effective 5/21/98. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, § 136-161-070, filed
8/12/96, effective 9/12/96. Statutory Authority: RCW 36.79.060. 94-16-111, § 136-161-070, filed 8/2/94, effective
9/2/94.]