WAC 136-161-060
RAP program cycle -- Total project rating
and priority array. County road administration board staff
will review all final prospectuses and ensure that:
(1) All necessary information is included;
(2) The project is from the pool of preliminary
prospectuses;
(3) The project is eligible for RATA funding;
(4) The project is on the current, adopted six-year
transportation program;
(5) The project schedule indicates that preliminary
engineering will begin not later than one year from the date
of project approval by the county road administration board,
and that the construction of the project will begin not later
than six years from the date of project approval by the county
road administration board; and
(6) The total project priority rating is mathematically
correct and the visual rating scores determined during the
field review are included.
(7) Existing and proposed roadway cross sections, project
narrative, and preconstruction photos are attached.
After county road administration board staff review, all
accepted final prospectuses within each region will be placed
in a declining total project rating array. After review by
the county road administration board at its next regular
meeting, the priority array for each region will be provided
to each county in the region. These arrays will be
preliminary only and will be provided to the counties to
assist them in their internal budgeting and programming. No
notations as to whether a particular project will or will not
be funded will be included.
[Statutory Authority: Chapter 36.78 RCW. 11-05-005, §
136-161-060, filed 2/3/11, effective 3/6/11. Statutory
Authority: Chapter 36.79 RCW. 99-01-021, § 136-161-060,
filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, § 136-161-060, filed
8/12/96, effective 9/12/96. Statutory Authority: RCW 36.79.060. 94-16-111, § 136-161-060, filed 8/2/94, effective
9/2/94.]