WAC 136-18-070
Special reporting
construction by county forces project to the
county road administration board. Each county engineer shall
submit to the county road administration board a copy of each
resolution authorizing a special reporting
construction by county forces road project whose estimated
construction cost exceeds seventy-five percent of the construction by county forces limit. Upon completion
of each of these projects, or no later than March 1st of the
succeeding year, the county engineer shall furnish to the
county road administration board a copy of the record of true
and complete construction costs. On any project where true
and complete construction costs have exceeded the statutory construction by county forces limit, the county
engineer shall also provide to the county road administration
board an explanation of the circumstances resulting in such
over-expenditure.
[Statutory Authority: Chapter 36.78 RCW. 09-23-044, §
136-18-070, filed 11/9/09, effective 12/10/09. Statutory
Authority: Chapter 36.79 RCW. 99-01-021, § 136-18-070, filed
12/7/98, effective 1/7/99. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, § 136-18-070, filed
8/12/96, effective 9/12/96. Statutory Authority: Chapter 36.78 RCW. 80-16-019 (Order 39), § 136-18-070, filed
10/29/80; 79-01-098 (Order 35), § 136-18-070, filed 1/3/79;
Order 27, § 136-18-070, filed 1/27/76.]