WAC 82-32-010
Contractor's option regarding retained
percentages. On all contracts for public improvements or work
for which retained percentages are required to be reserved
under the provisions of RCW 60.28.010, state agencies shall
require the contractor to exercise his option in writing on
whether or not moneys reserved from amounts due the contractor
shall be retained by the public body, deposited by the public
body in an interest bearing account in a bank, mutual savings
bank, or savings and loan association, or placed in escrow by
the public body. State agencies shall prescribe a procedure
for informing the contractor of the options available and the
method for exercising the option selected. Said option must
be exercised prior to or at time of submission of invoices for
the first progress payment to be made under the contract. No
progress payment shall be made until the contractor has
exercised his option in writing.
[Order 33, § 82-32-010, filed 7/19/76; Order 12, § 82-32-010,
filed 10/28/70.]