WAC 463-80-070
Carbon dioxide mitigation option
statement and mitigation plan submittal and approval. (1)
Applicants must provide EFSEC with a statement selecting the
mitigation option(s) in:
(a) Applications for site certification; or
(b) Requests to amend site certification agreements under
chapter 463-66 WAC where changes to the facility will increase
CO2 emissions by fifteen percent or more.
(2) Applicants choosing to use the payment to a third
party or the permanent carbon credit option must provide EFSEC
with the documentation to show how the requirements will be
satisfied before a recommendation to the governor is issued or
an amendment to a site certification agreement is approved.
(3) Applicants seeking to use the applicant controlled
mitigation projects option must submit the entire mitigation
plan to EFSEC. EFSEC will review the plan for consistency
with the requirements of chapter 80.70 RCW.
(4) Approval of the mitigation plan will be by:
(a) The governor for approval of the application for site
certification, or an amendment to the site certification
agreement under WAC 463-66-080; or
(b) EFSEC for approval of an amendment to the site
certification agreement under WAC 463-66-070.
[Statutory Authority: Chapters 80.70 and 80.80 RCW and RCW 80.50.040. 08-14-064, § 463-80-070, filed 6/25/08, effective
7/26/08.]