WAC 463-80-060
Carbon dioxide mitigation plan
requirements and options. (1) Once the total carbon dioxide
emissions mitigation quantity is calculated, what is next?
The facility must mitigate that level of carbon dioxide
emissions. A CO2 mitigation plan is required and must be
approved as part of a site certification agreement. A
mitigation plan is a proposal that includes the process or
means to achieve carbon dioxide mitigation through use of
mitigation projects or carbon credits (RCW 80.70.010).
The approved mitigation plan must be fully implemented
and operational in accordance with the schedule in the site
certification agreement. The applicant may request an
extension of the mitigation project implementation deadline.
The request must be submitted in writing to EFSEC before the
implementation deadline. The request must fully document the
reason(s) more time is needed to implement the mitigation
project and propose a revised schedule.
(2) What are the mitigation plan options? The options
are identified in RCW 80.70.020(3), which states that "An
applicant for a fossil-fueled thermal electric generation
facility shall include one or a combination of the following
carbon dioxide mitigation options as part of its mitigation
plan:
(a) Payment to a third party to provide mitigation;
(b) Direct purchase of permanent carbon credits; or
(c) Investment in applicant-controlled carbon dioxide
mitigation projects, including combined heat and power
(cogeneration)."
(3) What are the requirements of the payment to a
third-party option? The payment to a third party option
requirements are found in RCW 80.70.020 (5) and (6).
Subsection (5) identifies the mitigation rate for this option
and describes the process for changing the mitigation rate.
Subsection (6) describes the payment options.
The initial mitigation rate is $1.60 per metric ton of
carbon dioxide to be mitigated. If there is a cogeneration
plant, the monetary amount is based on the difference between
twenty percent of the total carbon dioxide emissions and the
cogeneration credit. The mitigation rate will change when
EFSEC adjusts it through the process described in RCW 80.70.020 (5)(a) and (b). The total payment
amount = mitigation rate x mitigation quantity.
An applicant may choose between a lump sum payment or
partial payment over a period of five years. The lump sum
payment is described in RCW 80.70.020 (6)(a) and (b). The
payment amount is the mitigation quantity multiplied by the
per ton mitigation rate. The entire payment amount is due to
the independent qualified organization no later than one
hundred twenty days after the start of commercial operation.
The alternative to a one-time payment is a partial
payment described in RCW 80.70.020 (6)(c). Under this
alternative, twenty percent of the total payment is due to the
independent qualified organization no later than one hundred
twenty days after the start of commercial operation. A
payment of the same amount (or an adjusted amount if the rate
is changed under RCW 80.70.020 (5)(a)) is due on the
anniversary date of the initial payment for the next four
consecutive years. In addition, the applicant is required to
provide a letter of credit or comparable security for the
remaining 80% at the time of the first payment. The letter of
credit (or comparable security) must also include possible
rate changes.
(4) What are the requirements of the permanent carbon
credits option? RCW 80.70.030 identifies the criteria and
specifies that these credits cannot be resold without approval
from EFSEC. The permanent carbon credit criteria of RCW 80.70.030(1) are as follows:
(a) Credits must derive from real, verified, permanent,
and enforceable carbon dioxide or carbon dioxide equivalents
emission mitigation not otherwise required by statute,
regulation, or other legal requirements;
(b) The credits must be acquired after July 1, 2004; and
(c) The credits may not have been used for other carbon
dioxide mitigation projects.
(5) What are the requirements for the
applicant-controlled mitigation projects option? RCW 80.70.040 identifies the requirements for applicant controlled
mitigation projects. Subsections (1) through (5) specify the
criteria. The direct investment cost of the applicant
controlled mitigation project including funds used for
selection, monitoring, and evaluation of mitigation projects
cannot be required by EFSEC to exceed the cost of making a
lump sum payment to a third party per subsection (3) of this
section.
The applicant controlled mitigation project must be:
(a) Implemented through mitigation projects conducted
directly by, or under the control of the site certification
agreement holder;
(b) Approved by EFSEC and incorporated as a condition of
the site certification agreement; and
(c) Operational within one year after the start of
commercial operation. Failure to implement an approved
mitigation plan is subject to enforcement under chapter 80.50 RCW.
(d) The certificate holder may not use more than twenty
percent of the total funds for the selection, monitoring, and
evaluation of mitigation projects, and the management and
enforcement of contracts.
[Statutory Authority: Chapters 80.70 and 80.80 RCW and RCW 80.50.040. 08-14-064, § 463-80-060, filed 6/25/08, effective
7/26/08.]