WAC 463-72-060
Site preservation plan -- Suspended
projects. In the event that construction is suspended, a plan
for site preservation shall be prepared at the earliest
feasible time, as agreed to by the council, and the council
shall be advised of interim concerns and the measures being
taken to remedy those concerns. The site preservation plan
shall address environmental, and public health and safety
concerns, the scope of proposed monitoring and the provisions
for funding or bonding to meet site preservation costs. It
shall describe measures that will be taken to preserve the
site or otherwise protect all segments of the public and
environment against risks or danger resulting from the site.
The preservation plan shall also address options for
preservation and the costs and benefits associated with those
options. The council will act on the plan at the earliest
feasible time and may take or require action as necessary to
deal with the extraordinary circumstances.
[Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013,
§ 463-72-060, filed 10/11/04, effective 11/11/04.]