WAC 463-61-100
Applications for site certification. (1)
An application for site certification may be submitted when
the preapplication process is completed. The preapplication
process shall be complete when:
(a) EFSEC has held one or more public meetings under WAC 463-61-060(3); and
(b) Negotiations between affected cities, towns, and/or
counties have been conducted and a corridor has been agreed
on; or
(c) Negotiations under WAC 463-61-080 have been conducted
but the preapplicant, cities, towns, and/or counties have not
agreed on a corridor and EFSEC has determined that
negotiations have failed.
(2) Applications for site certification of electrical
transmission lines under RCW 80.50.045 and 80.50.060 shall
follow the guidelines for applications for site certification
found in chapter 463-60 WAC.
[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 08-21-092, § 463-61-100, filed 10/15/08, effective 11/15/08.]