WAC 463-61-070
Corridors and transmission facilities
considerations. (1) EFSEC shall consider and may recommend
certification of electrical transmission facilities in
corridors designated for this purpose by affected cities,
towns, or counties where:
(a) Jurisdictions have identified electrical transmission
facility corridors as part of their land use plans and zoning
maps based on policies adopted in their plans.
(b) The proposed electrical transmission facility is
consistent with any adopted development regulations that
govern the siting of electrical transmission facilities in
such corridors.
(c) Contiguous jurisdictions and jurisdictions in which
related regional electrical transmission facilities are
located have either prior to or during the preapplication
process undertaken good faith efforts to coordinate the
locations of their corridors consistent with RCW 36.70A.100.
(2) If EFSEC determines that negotiations as required in
WAC 463-61-080 have failed, EFSEC shall consider the
applicant's proposed corridor and transmission facilities
consistent with RCW 80.50.090 and 80.50.100 taking into
consideration the positions of the preapplicant and the
affected cities, towns or counties.
[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 08-21-092, § 463-61-070, filed 10/15/08, effective 11/15/08.]