WAC 463-61-030
Applicability. (1) The provisions of
this chapter apply to the construction, reconstruction, or
modification of electrical transmission facilities in each of
the following circumstances:
(a) The facility is located in a national interest
electric transmission corridor as specified in RCW 80.50.045.
(b) The applicant(s) or preapplicant(s) choose to seek
certification under RCW 80.50.060 and the facility:
(i) Has a nominal voltage of at least one hundred fifteen
thousand volts; and
(ii) Is proposed to be located in a completely new
corridor which is located in more than one jurisdiction where
at least one such jurisdiction has promulgated land use plans
or zoning ordinances. The location of the terminus of the
facility or the location of an interconnection between the
facility and the existing electrical transmission grid in an
existing corridor does not disqualify a facility from
consideration under this subsection.
(c) The applicant(s) or preapplicant(s) choose to seek
certification under RCW 80.50.060 and the facility:
(i) Has a nominal voltage in excess of one hundred
fifteen thousand volts; and
(ii) Is proposed to be located outside an existing or
designated electrical transmission corridor identified in (a)
or (b) of this subsection.
(2) This section does not apply to normal maintenance and
repairs which do not increase the capacity or dimensions
beyond those specified in this section.
[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 08-21-092, § 463-61-030, filed 10/15/08, effective 11/15/08.]