WAC 463-60-165
Proposal -- Water supply. (1) Water intake
and conveyance facilities. The application shall describe the
location and type of water intakes, water lines, pipelines and
water conveyance systems, and other associated facilities
required for providing water to the energy facility for which
certification is being requested.
(2) Water supply and usage alternatives.
(a) The applicant shall consider water supply
alternatives, including use of reclaimed water, water reuse
projects, and conservation methods. The application shall
describe all supply alternatives considered, including the
associated cost of implementing such alternatives, and the
resulting benefits and penalties that would be incurred.
(b) The application shall include detailed information
regarding using air cooling as an alternative to consumptive
water use, including associated costs.
(c) The application shall describe water conservation
methods that will be used during construction and operation of
the facility.
(3) Water rights and authorizations. An applicant
proposing to use surface or ground water for the facility
shall describe the source and the amount of water required
during construction and operation of the energy facility and
shall do one or more of the following:
(a) Submit a water use authorization or a contractual
right to use water supplied by a municipal corporation or
other water purveyor; or
(b) Submit a water right permit or water right
certificate issued by the department of ecology for the
proposed facility in an amount sufficient to meet the need of
the facility. If the permit and/or certificate has been
issued five years prior to the submittal date, the applicant
shall provide evidence that the water right permit is in good
standing, or that the certificate has not relinquished through
nonuse; or
(c) For applications for new surface or ground water
withdrawals, or applications for water right changes or
transfers of existing rights or certificates for withdrawal,
the applicant shall submit appropriate application(s) for such
rights, certificates or changes in rights and certificates, to
the department of ecology prior to submittal of the
application for site certification to the council. The
application for site certification shall include report(s) of
examination, identifying the water rights, or water right
changes, submitted to and under review by the department of
ecology, the quantities of water in gallons per minute and
acre feet per year that are eligible for change, together with
any limitations on use, including time of year. The report(s)
of examination shall also include comments by the Washington
state department of fish and wildlife with respect to the
proposed water right applications under review by the
department of ecology.
(d) Mitigation. The application shall contain a
description of mitigation proposed for water supply, and shall
include any and all mitigation required by the department of
ecology pursuant to the review of water rights or
certificates, or changes to water rights or certificates
required in (c) of this subsection.
[Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013,
amended and recodified as § 463-60-165, filed 10/11/04,
effective 11/11/04. Statutory Authority: RCW 80.50.040(1). 92-09-013, § 463-42-165, filed 4/2/92, effective 5/3/92. Statutory Authority: RCW 80.50.040(1) and chapter 80.50 RCW. 81-21-006 (Order 81-5), § 463-42-165, filed 10/8/81. Formerly
WAC 463-42-400.]