WAC 463-60-160
Proposal -- Electrical transmission facilities. (1) Prior to submitting an application for site
certification for an electric transmission facility under RCW 80.50.060(3) an applicant shall follow the procedure as set in
chapter 463-61 WAC.
(2) An application for an electric transmission facility
shall include the information required by this chapter unless
the requirement may not be applicable to such a facility.
(3) An application for an electrical transmission
facility shall include the results of any preapplication
negotiations including any agreements between the applicant
and cities, towns, or counties where the electrical
transmission facility is proposed to be located.
[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 09-05-067, § 463-60-160, filed 2/13/09, effective 3/16/09.]