WAC 463-58-065
Costs for preapplication process for
electrical transmission facilities. Pursuant to RCW 80.50.340, ten thousand dollars shall accompany any
preapplication request. If the council determines that the
initial ten thousand dollars is insufficient to adequately
fund the preapplication process, the council shall so advise
the potential applicant and shall provide an estimate of the
supplemental cost needed to complete the study. In no event
shall the study be allowed to continue if the potential
applicant has not agreed to pay the cost of the study. Any
unexpended funds shall be returned to the preapplicant.
[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 09-05-067, § 463-58-065, filed 2/13/09, effective 3/16/09.]