WAC 463-43-060   Effect of expedited processing.  For an application granted expedited processing under WAC 463-43-050 the council shall not:

     (1) Conduct any further review of an application by an independent consultant; however, at the direction of the council an independent consultant may prepare air or water discharge permits or other ancillary permits or studies that may be needed as part of a recommendation to the governor;

     (2) Hold an adjudicative proceeding under chapter 34.05 RCW; and

     (3) Continue an adjudicative proceeding that has commenced.



[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 09-05-067, § 463-43-060, filed 2/13/09, effective 3/16/09. Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013, § 463-43-060, filed 10/11/04, effective 11/11/04. Statutory Authority: RCW 80.50.040. 91-03-090, § 463-43-060, filed 1/18/91, effective 2/18/91. Statutory Authority: RCW 80.50.071. 78-05-054 (Order 78-2), § 463-43-060, filed 4/26/78.]