WAC 463-43-040
Prior to making a determination of
eligibility for expedited processing. The council prior to
making a determination of eligibility for expedited processing
shall:
(1) Conduct a public informational meeting in the county
of the proposed site within sixty days of receipt of an
application to provide information to the public concerning
the nature and purpose of the energy facility and the review
process to be undertaken by the council and to provide an
opportunity for the public to present its views;
(2) Determine at a public hearing within sixty days of
receipt of an application if the proposed site is consistent
and in compliance with city, county or regional land use plans
and zoning ordinances;
(3) Review the application pursuant to WAC 463-43-030; in
making its review the council may engage pursuant to RCW 80.50.071 (1)(a) an independent consultant to provide an
assessment of the application and environmental checklist and
to conduct any special study deemed necessary by the council;
and
(4) If applicable, initiate processing of:
(a) A NPDES application in accordance
with chapter 463-76 WAC;
(b) An air emissions or PSD permit application in
accordance with 463-78 WAC;
(c) Other such authorizations or permits as may be
required by law or rule and necessary for construction and
operation of the project.
[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. 09-05-067, § 463-43-040, filed 2/13/09, effective 3/16/09. Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013,
§ 463-43-040, filed 10/11/04, effective 11/11/04. Statutory
Authority: RCW 80.50.071. 78-05-054 (Order 78-2), §
463-43-040, filed 4/26/78.]