WAC 463-28-060
Adjudicative proceeding. (1) Should the
council determine under WAC 463-26-110 a site or any portions
of a site is inconsistent it will schedule an adjudicative
proceeding under chapter 463-30 WAC to consider preemption.
(2) The proceeding for preemption may be combined or
scheduled concurrent with the adjudicative proceeding held
under RCW 80.50.090(3).
(3) The council shall determine whether to recommend to
the governor that the state preempt the land use plans, zoning
ordinances, or other development regulations for a site or
portions of a site for the energy facility or alternative
energy resource proposed by the applicant.
[Statutory Authority: RCW 80.50.040(1). 07-21-035, §
463-28-060, filed 10/9/07, effective 11/9/07. Statutory
Authority: RCW 80.50.040. 91-03-090, § 463-28-060, filed
1/18/91, effective 2/18/91. Statutory Authority: RCW 80.50.040(1). 83-08-031 (Order 83-2), § 463-28-060, filed
3/31/83; 78-07-036 (Order 78-3), § 463-28-060, filed 6/23/78.]