WAC 463-22-050
Retention of consultant. Upon receipt of
a request for a potential site study, the council shall
commission an independent consultant of its choice to study
and report in writing to the council on the potential site. The report of study shall set forth a general analysis of the
potential environmental impact of the proposed energy facility
and shall identify significant areas of environmental concern.
The study may also encompass whatever other matters the
council and potential applicant deem essential for an adequate
appraisal of the potential site and potentially impacted areas
surrounding or adjacent to the site.
[Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013,
§ 463-22-050, filed 10/11/04, effective 11/11/04; Order 106, §
463-22-050, filed 11/4/76.]