WAC 352-11-330
Threshold determination
process -- Additional considerations. (1) Applicants are
required to fully complete an environmental checklist to aid
the agency in rendering a threshold determination.
(2)(a) To make the final determination, the responsible
official will consider: All comments received, mitigation
measures proposed, and suggested changes to the project.
(b) If there are substantial changes to the project
during the SEPA process, the final determination must undergo
similar public notice as the initial determination. Projects
without changes or only minor changes do not require public
notice of a final determination.
[Statutory Authority: Chapter 79A.05 RCW. 07-03-121, §
352-11-330, filed 1/22/07, effective 2/22/07.]