WAC 296-127-01370
Roofers. For the purpose of the
Washington state public works law, chapter 39.12 RCW, roofers
apply and install any and all types of roofing materials, other
than sheet metal. The work of roofers includes, but is not
limited to:
(1) The installation of slate and tile and all substitute
materials taking the place of slate and tile, with necessary
metal flashing to make water-tight.
All cementing in, on or around slate and tile roofs.
All laying of felt or paper beneath the slate and tile.
All dressing, punching and cutting of all roof slate or tile
either by hand or machinery.
(2) The installation of all forms of plastic, slate, slag,
gravel; asphalt and composition roofing; rock asphalt mastic when
used for damp and waterproofing; prepared paper; compressed
paper, and chemically prepared paper with or without coating.
The installation of all damp resisting preparations when
applied on roofs with mop, three-knot brush, roller, swab or
spray system.
(3) The installation of all forms of elastomeric and/or
plastic (elasto-plastic) roofing systems, both sheet and liquid
applied, whether single-ply or multi-ply.
All types of aggregates, blocks, bricks or stones used to
ballast these elasto-plastic systems.
All types of aggregates used as a ballast for inverted
roofing membrane assembly, or roof of similar construction where
the insulation is laid over the roofing membrane.
All sealing and caulking of seams and joints on these
elasto-plastic systems to insure water-tightness.
All liquid-type elasto-plastic preparation for roofing, damp
or waterproofing when applied with a squeegee, trowel, roller or
spray equipment.
All sheet-type elasto-plastic systems, whether single or
multi-ply, for waterproofing.
All priming of surfaces to be roofed, damp or waterproofed,
whether done by roller, mop, swab, three-knot brush, or spray
systems.
All types of preformed panels used in waterproofing.
(4) The application of all types of spray-in-place foams
such as urethane or polyurethane, and the coatings that are
applied over them.
(5) The application of roof insulation, when the insulation
material is applied as an integral part of the roofing system,
whether the insulation material is applied as the first, last or
any other layer in between.
(6) The handling, hoisting and storing of all roofing, damp
and waterproofing materials.
(7) The tear-off and/or removal of any type of roofing,
including roofing materials containing asbestos, all spudding,
sweeping, vacuuming and/or cleanup of any and all areas of any
type where a roof is to be relayed, and all other cleanup
required in connection with roofing work.
[Statutory Authority: Chapter 39.12 RCW, RCW 43.22.270 and 43.22.051. 00-15-077, § 296-127-01370, filed 7/19/00, effective
7/19/00.]