WAC 246-290-125
Project report and construction document
submittal exceptions. (1) The following projects do not
require project reports under WAC 246-290-110 and construction
documents under WAC 246-290-120 to be submitted to the
department for review and approval prior to installation:
(a) Installation of valves, fittings, and meters,
including backflow prevention assemblies;
(b) Installation of hydrants under WAC 246-290-230 (3)
and (6);
(c) Repair of a system component or replacement with a
component of a similar capacity and material in accordance
with the original construction specifications of the approved
design. For the purposes of replacing existing pipe, similar
capacity includes one standard pipe size larger.
(d) Maintenance or painting of surfaces not contacting
potable water.
(2) Purveyors may elect to not submit to the department
for review and approval project reports under WAC 246-290-110
and construction documents under WAC 246-290-120 for new
distribution mains if:
(a) The purveyor has on file with the department a
current department-approved water system plan that includes
standard construction specifications for distribution mains;
and
(b) The purveyor maintains on file a completed
construction completion report (department form) in accordance
with WAC 246-290-120(5) and makes it available for review upon
request by the department.
(3) Purveyors may elect to not submit to the department
for review and approval project reports under WAC 246-290-110
and construction documents under WAC 246-290-120 for review
and approval of other distribution-related projects as defined
in WAC 246-290-010 providing:
(a) The purveyor has on file with the department a
current department-approved water system plan, in accordance
with WAC 246-290-100(5);
(b) The purveyor submits a written request with a new
water system plan or an amendment to a water system plan, and
updates the request with each water system plan update. The
written request should specifically identify the types of
projects or facilities for which the submittal exception
procedure is requested;
(c) The purveyor has documented that they have employed
or hired under contract the services of a professional
engineer licensed in the state of Washington to review
distribution-related projects not submitted to the department
for review and approval. The review engineer and design
engineer shall not be the same individual. The purveyor shall
provide written notification to the department whenever they
propose to change their designated review engineer;
(d) If the project is a new transmission main, storage
tank, or booster pump station, it must be identified in the
capital improvement program of the utility's water system
plan. If not, either the project report must be submitted to
the department for review and approval, or the water system
plan must be amended;
(e) A project summary file is maintained by the purveyor
for each project and made available for review upon request by
the department, and includes:
(i) Descriptive project summary;
(ii) Anticipated completion schedule;
(iii) Consistency with utility's water system plan;
(iv) Water right self-assessment, where applicable;
(v) Change in system physical capacity;
(vi) Copies of original design and record drawings;
(vii) Engineering design review report (department form).
The form shall:
(A) Bear the seal, date, and signature of a professional
engineer licensed in the state of Washington prior to the
start of construction;
(B) Provide a descriptive reference to completed project
report and/or construction documents reviewed, including date
of design engineer's seal and signature; and
(C) State the project report and/or construction
documents have been reviewed, and the design is in accordance
with department regulations and principles of standard
engineering practice;
(f) The construction completion report is submitted to
the department in accordance with WAC 246-290-120(5) for new
storage tanks and booster pump stations, and maintained on
file with the water system for all other distribution-related
projects;
(g) A WFI is completed in accordance with WAC 246-290-120(6); and
(h) The purveyor meets the requirements of chapter 246-294 WAC to have a category "green" operating permit.
(4) Source of supply (including interties) and water
quality treatment-related projects shall not be eligible for
the submittal exception procedure.
(5) Purveyors not required to prepare a water system plan
under WAC 246-290-100 shall be eligible for the submittal
exception procedure if the purveyor:
(a) Has a department-approved water system plan meeting
the requirements of WAC 246-290-100;
(b) Complies with all other requirements in this section;
and
(c) Ensures that all work required to be prepared under
the direction of a professional engineer be accomplished per
WAC 246-290-040 and chapter 18.43 RCW.
[Statutory Authority: RCW 70.119A.180 and 43.20.050. 08-03-061, § 246-290-125, filed 1/14/08, effective 2/14/08. Statutory Authority: RCW 43.20.050 (2) and (3) and70.119A.080
. 03-08-037, § 246-290-125, filed 3/27/03,
effective 4/27/03. Statutory Authority: RCW 43.02.050
[43.20.050]. 99-07-021, § 246-290-125, filed 3/9/99,
effective 4/9/99.]