WAC 222-24-040
Water crossing structures. *(1) General
provisions for all typed waters.
In addition to the applicable general provisions below,
installation, maintenance and removal of water crossing
structures in or across the bankfull width of Type S or F Waters
are subject to hydraulic code rules, chapter 220-110 WAC, and
require hydraulic project approval (HPA) issued by the department
of fish and wildlife. HPAs may be required on Type Ns and Np
Waters.
(a) Bridges are required for new crossings and reconstructed
crossings of any typed waters regularly used for recreational
boating.
(b) Structures containing concrete must be sufficiently
cured prior to contact with water.
(c) One end of each new or reconstructed permanent log or
wood bridge shall be tied or firmly anchored if any of the bridge
structure is within 10 vertical feet of the 100-year flood level.
(d) Alterations or disturbance of the stream bed, bank or
bank vegetation must be limited to that necessary to construct
the project. All disturbed areas must be stabilized and restored
according to the recommended schedule and procedures found in
section 3 of the board manual. This requirement may be modified
or waived by the department, in consultation with the department
of fish and wildlife, if precluded by engineering or safety
factors.
(e) When earthen materials are used for bridge surfacing,
only clean sorted gravel may be used, a geotextile lining must be
installed and curbs of sufficient size shall be installed to a
height above the surface material to prevent surface material
from falling into the stream bed.
(f) Wood removed from the upstream end of culverts and
bridges will be placed at the downstream end of such culverts and
bridges in such a way as to minimize obstruction of fish passage
and to the extent practical while avoiding significant
disturbance of sediment, in connection with maintenance
activities.
*(2) Bridges over Type Np and Ns Waters. In addition to
the applicable general provisions above, installation,
maintenance, and removal of permanent bridges in or across Type
Np and Ns Waters are subject to the following:
(a) Permanent bridges must not constrict clearly defined
channels and must be designed and installed to pass the 100-year
flood. The bridge and its associated embankments and fills must
provide sufficient erosion protection to withstand a 100-year
flood event.
(b) Excavation for and placement of the bridge foundation
and superstructure must be located and conducted from outside the
outer edge of the bankfull width. This requirement may be waived
by the department, in consultation with the department of fish
and wildlife, if it can be demonstrated that these activities may
be conducted in such a manner to prevent damage to public
resources.
(c) Earthen embankments constructed for use as bridge
approaches must be provided with sufficient erosion protection to
withstand a 100-year flood event.
*(3) Culvert installation for Type Np and Ns Waters. In
addition to applicable general provisions above, installation,
maintenance and removal of permanent culverts in or across Type
Np and Ns Waters are subject to the following provisions:
(a) All permanent culverts must be designed to pass the
100-year flood event with consideration for the passage of debris
likely to be encountered.
(b) The culvert and its associated embankments and fills
must have sufficient erosion protection to withstand the 100-year
flood event. Erosion protection may include armored overflows or
the use of clean coarse fill material.
(c) If the department determines that because of unstable
slopes the culvert size shown in the board manual, section 3,
"Determining Culvert Size, Method A" would be inadequate to
protect public resources, it may require a larger culvert
designed using generally accepted engineering principles that
meet the standards in (a) and (b) of this subsection.
(d) No permanent culverts shall be installed that are
smaller than:
(i) 24 inches for Type Np Waters.
(ii) 18 inches for Type Ns Waters in western Washington.
(iii) 15 inches for Type Ns Waters in eastern Washington.
(e) The alignment and slope of the culvert shall parallel
the natural flow of the stream whenever possible.
(f) Culverts must be designed and installed so they will not
cause scouring of the stream bed and erosion of the banks in the
vicinity of the project.
(g) When the department determines that installing a culvert
in a flowing stream will result in excessive siltation and
turbidity, and siltation and turbidity would be reduced if stream
flow were diverted, the department shall require the stream flow
be diverted using a bypass flume or culvert, or by pumping the
stream flow around the work area. This may include culvert
installations that are within 0.25 miles of a Type S or F Water
or within two miles of a hatchery intake in consultation with the
department of fish and wildlife.
(h) Fill associated with culvert installation must have
sufficient erosion protection to withstand the 100-year flood.
(i) Stream beds shall be cleared for a distance of 50 feet
upstream from the culvert inlet of such slash or debris that
reasonably may be expected to plug the culvert.
(j) The entrance of all culverts shall have adequate catch
basins and headwalls to minimize the possibility of erosion or
fill failure.
*(4) Temporary water crossings in Type Np and Ns Waters.
In addition to the applicable general provisions above,
installation, maintenance and removal of temporary bridges or
other structures in or across Type Np and Ns Waters are subject
to the following:
(a) A temporary water crossing is intended for use during
the life of an approved application/notification.
(b) It must be constructed to facilitate abandonment when
the intended use is complete or upon seasonal shutdown, whichever
is sooner.
(c) Temporary water crossings must be identified on the
forest practices application or notification, along with an
abandonment date.
(d) Temporary water crossings may be used:
(i) In western Washington if installed after June 1 and
removed by September 30 of the same year.
(ii) In eastern Washington if installed after the spring
runoff and removed prior to October 15th.
(iii) At other times, when the department and applicant can
agree to specific dates of installation and removal and the
extended dates result in equivalent levels of resource
protection.
(e) Temporary water crossings must be designed to pass the
highest peak flow event expected to occur during the length of
its intended use.
(f) When the department determines that installing a culvert
in a flowing stream will result in excessive siltation and
turbidity, and siltation and turbidity would be reduced if stream
flow were diverted, the department shall require the stream flow
be diverted using a bypass flume or culvert, or by pumping the
stream flow around the work area. This may include culvert
installations that are within 0.25 miles of a Type S or F Water
or within two miles of a hatchery intake, in consultation with
the department of fish and wildlife.
(g) Temporary water crossings shall be promptly removed and
abandoned to the specifications approved by the department upon
completion of use or by the date specified in the approved forest
practices application, whichever is earlier. Approaches to the
crossing shall be water barred and stabilized at the time of the
crossing removal. The department may waive removal of the water
crossing if the applicant secures an amended forest practices
application, and the structure and its approaches meet all of the
requirements of a permanent water crossing structure.
(h) Temporary wetland crossings shall be abandoned and
restored based on a written plan approved by the department prior
to construction.
(i) Temporary water crossings must be designed to provide
the same level of protection for public resources as provided by
rules during the length of its use.
*(5) Properly prepared and maintained fords may be used in
Type Np and Ns Waters during periods of low water.
(a) Entry and exit points for each ford must be located as
close to perpendicular along the stream as possible, but will not
exceed 100 feet upstream or downstream of each other. Approaches
to the ford will not run adjacent to the stream.
(b) Ford locations must be shown on the forest practices
application.
(c) Best management practices for construction, maintenance
and use will be utilized as appropriate or as required by
conditions on the approved forest practices application.
[Statutory Authority: Chapter 34.05 RCW, RCW 76.09.040,[76.09.]050
, [76.09.]370, 76.13.120(9). 01-12-042, § 222-24-040,
filed 5/30/01, effective 7/1/01. Statutory Authority: RCW 76.09.040 and chapter 34.05 RCW. 97-24-091, § 222-24-040, filed
12/3/97, effective 1/3/98. Statutory Authority: RCW 76.09.040,
76.09.170 and chapter 34.05 RCW. 94-01-134, § 222-24-040, filed
12/20/93, effective 1/1/94. Statutory Authority: RCW 76.09.060,
76.09.040 and chapter 34.05 RCW. 92-23-056, § 222-24-040, filed
11/17/92, effective 12/18/92. Statutory Authority: RCW 76.09.040, 76.09.050 and chapter 34.05 RCW. 92-15-011, §
222-24-040, filed 7/2/92, effective 8/2/92. Statutory Authority:
RCW 76.09.040. 87-23-036 (Order 535), § 222-24-040, filed
11/16/87, effective 1/1/88. Statutory Authority: RCW 76.09.040
and 76.09.050. 82-16-077 (Resolution No. 82-1), § 222-24-040,
filed 8/3/82, effective 10/1/82; Order 263, § 222-24-040, filed
6/16/76.]