WAC 222-20-015
Multiyear permits. (1) Where a watershed
analysis has been approved for a WAU under WAC 222-22-080,
landowner(s) may apply for a multiyear permit. The
information provided and level of detail must be comparable to
that required for a two-year permit. At a minimum, the
application must include:
(a) A description of the forest practices to be conducted
during the period requested for the permit, and a map(s)
showing their locations; and
(b) Prescriptions must be identified where operations are
proposed within or include areas of resource sensitivity.
(2) A landowner with an approved road maintenance and
abandonment plan (other than a checklist) may apply for a
multiyear permit to perform road maintenance, road
abandonment, and/or associated right of way timber harvest, if
the schedule for implementing the plan is longer than two
years.
(3) A landowner may apply for a multiyear permit to
perform an approved alternate plan.
[Statutory Authority: RCW 76.09.040, 76.09.010 (2)(d). 07-20-044, § 222-20-015, filed 9/26/07, effective 10/27/07. Statutory Authority: RCW 76.09.040. 06-11-112, § 222-20-015,
filed 5/18/06, effective 6/18/06. Statutory Authority:
Chapter 34.05 RCW, RCW 76.09.040, [76.09.]050, [76.09.]370,76.13.120
(9). 01-12-042, § 222-20-015, filed 5/30/01,