WAC 173-307-050
Due dates. Plans must be completed and
executive summaries must be submitted in accordance with the
following schedule:
(1) Hazardous waste generators who generated more than fifty
thousand pounds of hazardous waste in calendar year 1991 and
hazardous substance users who were required to report in 1991, by
September 1, 1992;
(2) Hazardous waste generators who generated between seven
thousand and fifty thousand pounds of hazardous waste in calendar
year 1992 and hazardous substance users who were required to
report for the first time in 1992, by September 1, 1993;
(3) Hazardous waste generators who generated between two
thousand six hundred forty and seven thousand pounds of hazardous
waste in 1993 and hazardous substance users who were required to
report for the first time in 1993, by September 1, 1994;
(4) Hazardous waste generators who have not been required to
complete a plan on or before September 1, 1994, shall complete a
plan by September 1 of the year following the first year that
they generate more than two thousand six hundred forty pounds of
hazardous waste; and
(5) Hazardous substance users who have not been required to
complete a plan on or before September 1, 1994, shall complete a
plan by September 1 of the year following the first year that
they are required to report under Section 313 of Title III of the
Superfund Amendments and Reauthorization Act.
[Statutory Authority: Chapter 70.95C RCW. 00-15-020 (Order
00-08), § 173-307-050, filed 7/11/00, effective 8/11/00;
91-08-041 (Order 90-57), § 173-307-050, filed 4/1/91, effective
5/2/91.]