WAC 173-306-345
Construction quality assurance plan. (1)
Before construction or modification, a detailed plan that shows
how adequate and competent construction inspection will be
provided to insure compliance with the requirements of this
chapter and the approved engineering documents must be submitted
to and approved by the department. The plan must be submitted
according to a schedule specified in the permit.
(2) The construction quality assurance plan shall include:
(a) A construction schedule summarizing planned construction
activities, noting sequence interrelationships, durations, and
terminations;
(b) A description of construction management, organization
management procedures, lines of communication, and
responsibility;
(c) A description of anticipated quality control testing,
including type of test, frequency, and who will perform the
tests;
(d) A description of the construction inspection program
including inspection responsibilities, anticipated inspection
frequency, deficiency resolution, and inspector qualifications;
and
(e) For monofills, a description of how WAC 173-306-440
(4)(d) is to be met.
[Statutory Authority: Chapter 70.138 RCW. 00-19-018 (Order
00-17), § 173-306-345, filed 9/8/00, effective 10/9/00;
90-10-047, § 173-306-345, filed 4/30/90, effective 5/31/90.]