WAC 173-245-070
Declaration of construction completion. (1) Within thirty days after the owner accepts the construction
or modification of a domestic wastewater facility, the
professional engineer in responsible charge of inspection of the
project shall submit to the department (a) one complete set of
record drawings or as-built drawings (b) a declaration stating
the facilities were constructed in accordance with the provisions
of the construction quality assurance plan and without
significant change from the department approved plans and
specifications.
(2) The declaration will be furnished by the department and
will be the same form as WAC 173-245-075, declaration of
construction of water pollution control facilities. The
submission of the declaration is not necessary for sewer line
extensions where the local government entity has received
approval of a general sewer plan and standard design criteria. (See also, WAC 173-240-090.)
[Statutory Authority: RCW 90.48.110. 00-15-019 (Order 00-07), §
173-245-070, filed 7/11/00, effective 8/11/00. Statutory
Authority: RCW 90.48.035. 87-04-020 (Order DE 86-34), §
173-245-070, filed 1/27/87.]