WAC 173-145-155
Approval of changes to written agreements. All flood control maintenance and comprehensive flood control
management planning (CFCMP) projects subject to the provisions of
this rule must be conducted in accordance
with the plans, specifications, and conditions approved by
ecology. Any contemplated changes during construction or
planning process that are significant deviations from
conditions of the approved agreement, must first be
submitted to ecology for approval. Any changes to the total cost
of the project following execution of the written agreement must
be submitted to ecology for approval before the
construction or the completion of the plan.
[Statutory Authority: RCW 86.26.105. 01-02-006 (Order 00-13), §
173-145-155, filed 12/21/00, effective 1/21/01. Statutory
Authority: Chapter 86.26 RCW. 87-04-022 (Order 86-36), §
173-145-155, filed 1/28/87.]