WAC 173-145-070
FCAAP project approval process. The
project approval process for the eligible municipal corporations'
applications includes the following in the general sequence
given.
(1) Ecology will review all projects for compliance with the
requirements under this chapter and chapter 86.26 RCW.
(2) Ecology shall consult with the state department of fish
and wildlife in the development of a project priority list. The
state department of natural resources, affected Indian tribes,
and other affected parties may review and comment on the proposed
project plans before the approval of those plans.
(3) Thirty days public notice must be given that the project
priority list will be the subject of a public hearing. Notice of
this hearing shall appear in the Washington State Register in
accordance with chapter 34.08 RCW.
(4) The project priority list will be available at the
shorelands and environmental assistance program of the department
of ecology, at least fifteen days before the public hearing.
(5) The public comments will be reviewed and ecology shall
approve the project priority list as proposed or as revised in
accordance with public comments.
(6) Ecology shall prepare and finalize the written
agreements with the counties.
(7) The counties shall prepare and finalize the written
agreements with the involved eligible municipal corporations
within the county.
(8) The applicant shall prepare the construction plans and
specifications for approval by the county engineer before
submitting them to ecology for review and approval of each
project for compliance with all requirements.
(9) The applicant shall acquire the necessary federal,
state, and local permits or authorizations along with any other
permission required to complete the project.
[Statutory Authority: RCW 86.26.105. 01-02-006 (Order 00-13), §
173-145-070, filed 12/21/00, effective 1/21/01. Statutory
Authority: Chapter 86.26 RCW. 87-04-022 (Order 86-36), §
173-145-070, filed 1/28/87; 85-14-002 (Order DE 85-10), §
173-145-070, filed 6/21/85.]