WAC 173-27-130
Filing with department. (1) All
applications for a permit or a permit revision shall be
submitted to the department upon a final decision by local
government. Final decision by local government shall mean the
order or ruling, whether it be an approval or denial, which is
established after all local administrative appeals related to
the permit have concluded or the opportunity to initiate such
appeals have lapsed.
(2) When a substantial development permit and a
conditional use or variance permit are required for a
development, the submittal on the permits shall be made
concurrently.
(3) A complete submittal shall consist of the following
documents and information:
(a) A copy of the complete application pursuant to WAC 173-27-180;
(b) Findings and conclusions that establish the basis for
the decision including but not limited to identification of
shoreline environment designation, applicable master program
policies and regulations and the consistency of the project
with appropriate review criteria for the type of permit(s) as
established in WAC 173-27-140 through 173-27-170;
(c) The final decision of the local government;
(d) The permit data sheet required by WAC 173-27-190; and
(e) Where applicable, local government shall also file
the applicable documents required by chapter 43.21C RCW, the
State Environmental Policy Act, or in lieu thereof, a
statement summarizing the actions and dates of such actions
taken under chapter 43.21C RCW.
(4) When the project has been modified in the course of
the local review process, plans or text shall be provided to
the department that clearly indicate the final approved plan.
(5) Submittal of substantial development permits,
conditional use permits, variances, rescissions and revisions
is complete when all of the documents required pursuant to
subsections (3) and (4) of this section have been received by
the department. If the department determines that the
submittal does not contain all of the documents and
information required by this section, the department shall
identify the deficiencies and so notify local government and
the applicant in writing. Ecology will not act on conditional
use permit or variance submittal until the material requested
in writing is submitted to the department.
(6) "Date of filing" of a local government final decision
involving approval or denial of a substantial development
permit is the date of actual receipt by the department of a
local government's final decision on the permit.
(7) "Date of filing" involving approval or denial of a
variance or conditional use permit, is the date of transmittal
of the department's final decision on the variance or
conditional use permit to local government and the applicant.
(8) The department shall provide a written notice to the
local government and the applicant of the "date of filing."
(9) Any decision on an application for a permit under the
authority of this section, whether it is an approval or a
denial, shall, concurrently with the transmittal of the ruling
to the applicant, be filed with the department and the
attorney general.
(10) When a permit has been appealed pursuant to RCW 90.58.180, upon conclusion of all review proceedings, a copy
of the final order shall be provided by the local government
to the department. When the project has been modified in the
course of the review proceeding, plans or text shall be
provided to the local government, consistent with the
provisions of WAC 173-27-180, that clearly indicate the final
approved plan and the local government shall reissue the
permit accordingly and submit a copy of the reissued permit
and supporting documents consistent with subsection (3) of
this section to the department for completion of the file on
the permit. The purpose of this provision is to assure that
the local and department files on the permit are complete and
accurate and not to provide a new opportunity for appeal of
the permit.
[Statutory Authority: RCW 90.58.030 (3)(e), 90.58.045,90.58.065
, 90.58.140(9), 90.58.143, 90.58.147, 90.58.200,90.58.355
, 90.58.390, 90.58.515, 43.21K.080, 71.09.250,71.09.342
, 77.55.181, 89.08.460, chapters 70.105D, 80.50 RCW. 07-02-086 (Order 05-12), § 173-27-130, filed 1/2/07, effective
2/2/07. Statutory Authority: RCW 90.58.140(3) and[90.58].200
. 96-20-075 (Order 95-17), § 173-27-130, filed
9/30/96, effective 10/31/96.]