WAC 136-400-100
Terms of county road
administration board/county contract. The county
road administration board/county contract shall include, but
not be limited to, the following provisions:
(1) Such contract must be signed and
returned to the county road administration board within
forty-five days of its mailing by the county road
administration board.
(2) The project will be constructed in accordance with:
(a) The information furnished to the county road
administration board; and
(b) The plans and specifications prepared under the
supervision of the county engineer.
(3) The county will notify the county road administration
board when a contract has been awarded, when
construction has started, and when the project has been
completed.
(4) The county road administration board will reimburse
counties based on progress vouchers received
and approved on individual projects, subject to the
availability of county ferry capital improvement funds
appropriated by the legislature.
(5) The county will reimburse the county road
administration board in the event that a project post audit
reveals ineligible expenditure of county ferry capital
improvement funds. Said funds will be returned to the county fuel tax account for distribution in
accordance with RCW 46.68.120.
[Statutory Authority: Chapter 36.79 RCW. 08-10-026, §
136-400-100, filed 4/28/08, effective 5/29/08; 99-01-021, §
136-400-100, filed 12/7/98, effective 1/7/99. Statutory
Authority: RCW 36.78.070 and 36.79.060. 96-17-013, §
136-400-100, filed 8/12/96, effective 9/12/96. Statutory
Authority: 1991 c 310 § 1(4). 91-21-138 (Order 85), §
136-400-100, filed 10/23/91, effective 11/23/91.]