(Effective Until July 1, 2010.)
WAC 51-51-0806
Section R806 -- Roof ventilation.
R806.4 Conditioned attic assemblies. This section is not
adopted.
[Statutory Authority: RCW 19.27.074, 19.27.020, and chapters 19.27 and 34.05 RCW. 07-01-090, § 51-51-0806, filed 12/19/06,
effective 7/1/07.]
(Effective July 1, 2010.)
WAC 51-51-0806
Section R806 -- Roof ventilation.
R806.4 Unvented attic assemblies. Unvented attic assemblies
(spaces between the ceiling joists of the top story and the
roof rafters) shall be permitted if all of the following
conditions are met:
1. The unvented attic space is completely contained
within the building thermal envelope.
2. No interior vapor retarders are installed on the
ceiling side (attic floor) of the unvented attic assembly.
3. Where wood shingles or shakes are used, a minimum
1/4-inch (6 mm) vented air space separates the shingles or
shakes and the roofing underlayment above the structural
sheathing.
4. Any air-impermeable insulation shall be a vapor
retarder, or shall have a vapor retarder coating or covering
in direct contact with the underside of the insulation.
5. Either items a, b or c below shall be met, depending
on the air permeability of the insulation directly under the
structural roof sheathing.
a. Air-impermeable insulation only. Insulation shall be
applied in direct contact to the underside of the structural
roof sheathing.
b. Air-permeable insulation only. In addition to the
air-permeable insulation installed directly below the
structural sheathing, rigid board or sheet insulation shall be
installed directly above the structural roof sheathing as
specified per Washington climate zone for condensation
control.
i. Climate Zone #1 - R-10 minimum rigid board or
air-impermeable insulation R-value.
ii. Climate Zone #2 - R-25 minimum rigid board or
air-impermeable insulation R-value.
c. Air-impermeable and air-permeable insulation. The
air-impermeable insulation shall be applied in direct contact
to the underside of the structural roof sheathing as specified
per Washington climate zone for condensation control. The
air-permeable insulation shall be installed directly under the
air-impermeable insulation.
i. Climate Zone #1 - R-10 minimum rigid board or
air-impermeable insulation R-value.
ii. Climate Zone #2 - R-25 minimum rigid board or
air-impermeable insulation R-value.
[Statutory Authority: RCW 19.27.031 and 19.27.074. 10-03-098, § 51-51-0806, filed 1/20/10, effective 7/1/10. Statutory Authority: RCW 19.27.074, 19.27.020, and chapters 19.27 and 34.05 RCW. 07-01-090, § 51-51-0806, filed 12/19/06,
effective 7/1/07.]