WAC 51-11-1150   Conflicts with other codes.  In case of conflicts among Codes enumerated in RCW 19.27.031 (1), (2), (3) and (4) and this Code, the first named Code shall govern. The duct insulation requirements in this Code or a local jurisdiction's energy code, whichever is more stringent, supersede the requirements in the Mechanical Code.

     Where, in any specific case, different sections of this Code specify different materials, methods of construction or other requirements, the most restrictive shall govern. Where there is a conflict between a general requirement and a specific requirement, the specific requirement shall be applicable.



[Statutory Authority: RCW 19.27A.020, 19.27A.045. 04-01-106, § 51-11-1150, filed 12/17/03, effective 7/1/04. Statutory Authority: RCW 19.27A.025. 93-21-052, § 51-11-1150, filed 10/18/93, effective 4/1/94.]