WAC 51-11-1143
Inspections.
1143.1 General: All construction or work for which a permit
is required shall be subject to inspection by the building
official and all such construction or work shall remain
accessible and exposed for inspection purposes until approved
by the building official. No work shall be done on any part
of the building or structure beyond the point indicated in
each inspection without first obtaining the approval of the
building official.
1143.2 Required Inspections: The building official, upon
notification, shall make the inspection required in this
Section, in addition to or as part of those inspections
required in Section 109.3 of the International Building Code. Inspections may be conducted by special inspection pursuant to
Section 1704 of the International Building Code. Where
applicable, inspections shall include at least:
1143.2.1 Envelope
a. Wall Insulation Inspection: To be made after all wall
insulation and air vapor retarder sheet or film materials are
in place, but before any wall covering is placed.
b. Glazing Inspection: To be made after glazing
materials are installed in the building.
c. Exterior Roofing Insulation: To be made after the
installation of the roof insulation, but before concealment.
d. Slab/Floor Insulation: To be made after the
installation of the slab/floor insulation, but before
concealment.
1143.2.2 Mechanical
a. Mechanical Equipment Efficiency and Economizer: To be
made after all equipment and controls required by this Code
are installed and prior to the concealment of such equipment
or controls.
b. Mechanical Pipe and Duct Insulation: To be made after
all pipe and duct insulation is in place, but before
concealment.
1143.2.3 Lighting and Motors
a. Lighting Equipment and Controls: To be made after the
installation of all lighting equipment and controls required
by this Code, but before concealment of the lighting
equipment.
b. Motor Inspections: To be made after installation of
all equipment covered by this Code, but before concealment.
1143.3 Reinspection: The building official may require a
structure to be reinspected. A reinspection fee may be
assessed for each inspection or reinspection when such portion
of work for which inspection is called is not complete or when
corrections called for are not made.
[Statutory Authority: RCW 19.27A.020, 19.27A.045. 04-01-106,
§ 51-11-1143, filed 12/17/03, effective 7/1/04. Statutory
Authority: Chapters 19.27 and 19.27A RCW and 1994 c 226. 95-01-126, § 51-11-1143, filed 12/21/94, effective 6/30/95. Statutory Authority: RCW 19.27A.025. 93-21-052, §
51-11-1143, filed 10/18/93, effective 4/1/94.]