Chapter 16.12
FLOOD DAMAGE PREVENTION

Sections:

16.12.005    Statutory authorization.

16.12.010    Findings of fact.

16.12.020    Statement of purpose.

16.12.030    Methods of reducing flood losses.

16.12.040    Definitions.

16.12.050    General provisions.

16.12.060    Administration.

16.12.070    Provisions for flood hazard reduction – General standards.

16.12.080    Provisions for flood hazard reduction – Specific standards.

16.12.090    Encroachments.

16.12.100    Critical facility.

16.12.005 Statutory authorization.

The Legislature of the state of Washington has in the city of Shoreline delegated the responsibility to local governmental units to adopt regulations designed to promote the public health, safety, and general welfare of its citizenry. Therefore, the city of Shoreline does ordain as follows:

A. Restricting or prohibiting uses which are dangerous to health, safety, and property due to water or erosion hazards, or which result in damaging increases in erosion or in flood heights or velocities;

B. Requiring that uses vulnerable to floods, including facilities which serve such uses, be protected against flood damage at the time of initial construction;

C. Controlling the alteration of natural floodplains, stream channels, and natural protective barriers, which help accommodate or channel flood waters;

D. Controlling filling, grading, dredging, and other development which may increase flood damage; and

E. Preventing or regulating the construction of flood barriers which will unnaturally divert flood waters or may increase flood hazards in other areas. [Ord. 115 § 1.1, 1997]

16.12.010 Findings of fact.

A. The flood hazard areas of the city of Shoreline are subject to periodic inundation which results in loss of life and property, health and safety hazards, disruption of commerce and governmental services, extraordinary public expenditures for flood protection and relief, and impairment of the tax base, all of which adversely affect the public health, safety and general welfare.

B. These flood losses are caused by the cumulative effect of obstructions in areas of special flood hazards which increase flood heights and velocities and, when inadequately anchored, damage uses in other areas. Uses that are inadequately floodproofed, elevated, or otherwise protected from flood damage also contribute to the flood loss. [Ord. 115 § 1.2, 1997]

16.12.020 Statement of purpose.

It is the purpose of this chapter to promote the public health, safety and general welfare, and to minimize public and private losses due to flood conditions in specific areas by provisions designed:

A. To protect human life and health;

B. To minimize expenditure of public money and costly flood control projects;

C. To minimize the need for rescue and relief efforts associated with flooding and generally undertaken at the expense of the general public;

D. To minimize prolonged business interruptions;

E. To minimize damage to public facilities and utilities such as water and gas mains, electric, telephone and sewer lines, streets and bridges located in areas of special flood hazard;

F. To help maintain a stable tax base by providing for the sound use and development of areas of special flood hazard so as to minimize future flood blight areas;

G. To ensure that potential buyers are notified that property is in an area of special flood hazard; and

H. To ensure that those who occupy the areas of special flood hazard assume responsibility for their actions. [Ord. 115 § 1.3, 1997]

16.12.030 Methods of reducing flood losses.

In order to accomplish its purposes, this chapter includes methods and provisions for:

A. Restricting or prohibiting uses which are dangerous to health, safety and property due to water or erosion hazards, or which result in damaging increases in erosion or in flood heights or velocities;

B. Requiring that uses vulnerable to floods, including facilities which serve such uses, be protected against flood damage at the time of initial construction;

C. Controlling the alteration of natural floodplains, stream channels, and natural protective barriers, which help accommodate or channel floodwaters;

D. Controlling filling, grading, dredging and other development which may increase flood damage; and

E. Preventing or regulating the construction of flood barriers which will unnaturally divert floodwaters or may increase flood hazards in other areas. [Ord. 115 § 1.4, 1997]

16.12.040 Definitions.

Unless specifically defined in this section, words or phrases used in this chapter shall be interpreted so as to give them the meaning they have in common usage and to give this chapter its most reasonable application.

1. “Appeal” means a request for a review of the building official’s interpretation of any provision of this chapter or a request for a variance.

2. “Area of shallow flooding” means a designated AO or AH zone on the flood insurance rate map (FIRM). The base flood depths range from one to three feet; a clearly defined channel does not exist; the path of flooding is unpredictable and indeterminate; and, velocity flow may be evident. AO is characterized as sheet flow and AH indicates ponding.

3. “Area of special flood hazard” means the land in the floodplain within a community subject to a one percent or greater chance of flooding in any given year. Designation on maps always includes the letters A or V.

4. “Base flood” means the flood having a one percent chance of being equaled or exceeded in any given year. Also referred to as the “100-year flood.” Designation on maps always includes the letters A or V.

5. “Basement” means any area of the building having its floor subgrade (below ground level) on all sides.

6. “Breakaway wall” means a wall that is not part of the structural support of the building and is intended through its design and construction to collapse under specific lateral loading forces, without causing damage to the elevated portion of the building or supporting foundation system.

7. “City” means city of Shoreline.

8. “Coastal high hazard area” means an area of special flood hazard extending from offshore to the inland limit of a primary frontal dune along an open coast and any other area subject to high velocity wave action from storms or seismic sources. The area is designated on the FIRM as zone V1-V30, VE, or V.

9. “Critical facility” means a facility for which even a slight chance of flooding might be too great. Critical facilities include, but are not limited to, schools, nursing homes, hospitals, police, fire and emergency response installations, installations which produce, use, or store hazardous materials or hazardous waste.

10. “Development” means any manmade change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations located within the area of special flood hazard.

11. “Elevated building” means, for insurance purposes, a nonbasement building which has its lowest elevated floor raised above ground level by foundation walls, shear walls, post, piers, pilings, or columns.

12. “Existing manufactured home park or subdivision” means a manufactured home park subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed before the effective date of the adopted floodplain management regulations.

13. “Expansion to an existing manufactured home park or subdivision” means the preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads).

14. “Flood” or “flooding” means a general and temporary condition of partial or complete inundation of normally dry land areas from:

a. The overflow of inland or tidal waters; and/or

b. The unusual and rapid accumulation of runoff of surface waters from any source.

15. “Flood insurance rate map (FIRM)” means the official map on which the Federal Insurance Administration has delineated both the areas of special flood hazards and the risk premium zones applicable to the community.

16. “Flood insurance study” means the official report provided by the Federal Insurance Administration that includes flood profiles, the flood boundary-floodway map, and the water surface elevation of the base flood.

17. “Floodway” means the channel of a river or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than one foot.

18. “Lowest floor” means the lowest floor of the lowest enclosed area (including basement). An unfinished or flood resistant enclosure, usable solely for parking of vehicles, building access or storage, in an area other than a basement area, is not considered a building’s lowest floor; provided, that such enclosure is not built so as to render the structure in violation of the applicable nonelevation design requirements of this chapter found at SMC 16.12.080(A)(2).

19. “Manufactured home” means a structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when attached to the required utilities. The term “manufactured home” does not include a “recreational vehicle.”

20. “Manufactured home park or subdivision” means a parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.

21. “New construction” means structures for which the “start of construction” commenced on or after the effective date of the ordinance codified in this chapter.

22. “New manufactured home park or subdivision” means a manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after the effective date of adopted floodplain management regulations.

23. “Recreational vehicle” means a vehicle which is:

a. Built on a single chassis;

b. Four hundred square feet or less when measured at the largest horizontal projection;

c. Designed to be self-propelled or permanently towable by a light duty truck; and

d. Designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.

24. “Start of construction” includes substantial improvement, and means the date the building permit was issued; provided the actual start of construction, repair, reconstruction, placement or other improvement was within 180 days of the permit date. The actual start means either the first placement of permanent construction of a structure on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond the stage of excavation; or the placement of a manufactured home on a foundation. “Permanent construction” does not include land preparation, such as clearing, grading and filling; nor does it include the installation of streets and/or walkways; nor does it include excavation for a basement, footings, piers or foundation or the erection of temporary forms, nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure. For “substantial improvement” the actual start of construction means the first alteration of any wall, ceiling, floor, or other structural part of a building, whether or not that alteration affects the external dimensions of the building.

25. “Structure” means a walled and roofed building including a gas or liquid storage tank that is principally above ground.

26.  “Substantial damage” means damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damaged condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.

27. “Substantial improvement” means any repair, reconstruction or improvement of a structure, the cost of which equals or exceeds 50 percent of the market value of the structure either:

a. i. Before the improvement or repair is started; or

ii. If the structure has been damaged and is being restored, before the damage occurred. For the purposes of this definition “substantial improvement” is considered to occur when the first alteration of any wall, ceiling, floor or other structural part of the building commences, whether or not that alteration affects the external dimensions of the structure.

b. The term “substantial improvement” does not, however, include either:

i. Any project for improvement of a structure to comply with existing state or local health, sanitary or safety code specifications which are solely necessary to assure safe living conditions; or

ii. Any alteration of a structure listed on the National Register of Historic Places or a State Inventory of Historic Places.

28. “Variance” means a grant of relief from the requirements of this chapter which permits construction in a manner that would otherwise be prohibited by this chapter.

29. “Water dependent” means a structure for commerce or industry which cannot exist in any other location and is dependent on the water by reason of the intrinsic nature of its operations. [Ord. 115 § 2, 1997]

16.12.050 General provisions.

A. Lands to Which This Chapter Applies. This chapter shall apply to all areas of special flood hazards within the jurisdiction of the city.

B. Basis for Establishing the Areas of Special Flood Hazard. The areas of special flood hazard identified by the Federal Insurance Administration in a scientific and engineering report entitled “The Flood Insurance Study for King County, Washington” dated May 16, 1995, as amended, with accompanying flood insurance maps, as amended, are hereby adopted by reference and declared to be a part of the ordinance codified in this chapter. The flood insurance study is on file at the offices of the development services group.

C. Penalties for Noncompliance. No structure or land shall hereafter be constructed, located, extended, converted or altered without full compliance with the terms of this chapter and other applicable regulations. Violations of the provisions of this chapter by failure to comply with any of its requirements (including violations of conditions and safeguards established in connection with conditions) shall constitute a misdemeanor. Any person who violates this chapter or fails to comply with any of its requirements shall upon conviction thereof be fined not more than $1,000 or imprisoned for not more than 30 days, or both, for each violation, and in addition shall pay all costs and expenses involved in the case. Nothing contained in this chapter shall prevent the city of Shoreline from taking such other lawful action as is necessary to prevent or remedy any violation.

D. Abrogation and Greater Restrictions. This chapter is not intended to repeal, abrogate or impair any existing easements, covenants or deed restrictions. However, where this chapter and another ordinance, easement, covenant or deed restriction conflict or overlap, whichever imposes the more stringent restrictions shall prevail.

E. Interpretation. In the interpretation and application of this chapter, all provisions shall be:

1. Considered as minimum requirements;

2. Liberally construed in favor of the governing body; and

3. Deemed neither to limit nor repeal any other powers granted under state statutes.

F. Warning and Disclaimer of Liability. The degree of flood protection required by this chapter is considered reasonable for regulatory purposes and is based on scientific and engineering considerations. Larger floods can and will occur on rare occasions. Flood heights may be increased by manmade or natural causes. This chapter does not imply that land outside the areas of special flood hazards or uses permitted within such areas will be free from flooding or flood damages. This chapter shall not create liability on the part of the city, any officer or employee thereof, or the Federal Insurance Administration for any flood damages that result from reliance on this chapter or any administrative decision lawfully made under this chapter. [Ord. 115 § 3, 1997]

16.12.060 Administration.

A. Establishment of Development Permit.

1. Development Permit Required. A development permit shall be obtained before construction or development begins within any area of special flood hazard established in SMC 16.12.050 (B). The permit shall be for all structures including manufactured homes, as set forth in SMC 16.12.040, Definitions, and for all development including fill and other activities, also as set forth in SMC 16.12.040, Definitions.

2. Application for Development Permit. Application for a development permit shall be made on forms furnished by the city and may include but not be limited to plans in duplicate drawn to scale showing the nature, location, dimensions and elevations of the area in question; existing or proposed structures, fill, storage of materials, drainage facilities and the location of the foregoing. Specifically, the following information is required:

a. Elevation in relation to mean sea level of the lowest floor (including basement) of all structures;

b. Elevation in relation to mean sea level to which any structure has been floodproofed;

c. Certification by a registered professional engineer or architect that the floodproofing methods for any nonresidential structure meet the floodproofing criteria in SMC 16.12.080(B); and

d. Description of the extent to which a watercourse will be altered or relocated as a result of proposed development.

B. Designation of the Local Administrator. The development services director is appointed to administer and implement this chapter by granting or denying development permit applications in accordance with its provisions.

C. Duties and Responsibilities of the Local Administrator. Duties of the development services director shall include, but not be limited to:

1. Permit Review.

a. Review all development permits to determine that the permit requirements of this chapter have been satisfied.

b. Review all development permits to determine that all necessary permits have been obtained from those federal, state or local governmental agencies from which prior approval is required.

c. Review all development permits to determine if the proposed development is located in the floodway. If located in the floodway, assure that the encroachment provisions of SMC 16.12.090 are met.

2. Use of Other Base Flood Data. When base flood elevation data has not been provided in accordance with SMC 16.12.050(B), Basis For Establishing the Areas of Special Flood Hazard, the development services director shall obtain, review and reasonably utilize any base flood elevation and floodway data available from a federal, state or other source, in order to administer SMC 16.12.080, Provisions for flood hazard reduction – Specific standards.

3. Information to be Obtained and Maintained.

a. Where base flood elevation data is provided through the flood insurance study or required as in subsection (C)(2) of this section, obtain and record the actual elevation (in relation to mean sea level) of the lowest floor (including basement) of all new or substantially improved structures, and whether or not the structure contains a basement.

b. For all new or substantially improved floodproofed structures:

i. Verify and record the actual elevation (in relation to mean sea level); and

ii. Maintain the floodproofing certifications required in subsection (A)(2)(c) of this section.

c. Maintain for public inspection all records pertaining to the provisions of this chapter.

4. Alteration of Watercourses.

a. Notify adjacent communities and the Department of Ecology prior to any alteration or relocation of a watercourse, and submit evidence of such notification to the Federal Insurance Administration.

b. Require that maintenance is provided within the altered or relocated portion of such watercourse so that the flood carrying capacity is not diminished.

5. Interpretation of FIRM Boundaries. Make interpretations where needed, as to exact location of the boundaries of the areas of special flood hazards (for example, where there appears to be a conflict between a mapped boundary and actual field conditions). The person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation. Such appeals shall be granted consistent with the standards of Section 60.6 of the Rules and Regulations of the National Flood Insurance Program (44 CFR 59-76). Appeals shall be heard by the city hearing examiner in accordance with Chapter 2.15 SMC.

D. Variance Procedure – Conditions for Variances.

1. Generally, the only condition under which a variance from the elevation standard may be issued is for new construction and substantial improvements to be erected on a lot of one-half acre or less in size contiguous to and surrounded by lots with existing structures constructed below the base flood level, providing the provisions of this chapter have been fully considered. As the lot size increases the technical justification required for issuing the variance increases.

2. Variances may be issued for the reconstruction, rehabilitation or restoration of structures listed on the National Register of Historic Places or the State Inventory of Historic Places, without regard to the procedures set forth in this section.

3. Variances shall not be issued within a designated floodway if any increase in flood levels during the base flood discharge would result.

4. Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief.

5. Variances shall only be issued upon:

a. A showing of good and sufficient cause;

b. A determination that failure to grant the variance would result in exceptional hardship to the applicant;

c. A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisances, cause fraud on or victimization of the public as identified in this chapter, or conflict with existing local laws or ordinances.

6. Variances as interpreted in the National Flood Insurance Program are based on the general zoning law principle that they pertain to a physical piece of property; they are not personal in nature and do not pertain to the structure, its inhabitants, economic or financial circumstances. They primarily address small lots in densely populated residential neighborhoods. As such, variances from the flood elevations should be quite rare.

7. Variances may be issued for nonresidential buildings in very limited circumstances to allow a lesser degree of floodproofing than watertight or dry-floodproofing, where it can be determined that such action will have low damage potential, complies with all other variance criteria, and otherwise complies with SMC 16.12.070(A) and (B), Provisions for flood hazard reduction – General standards.

8. Any applicant to whom a variance is granted shall be given written notice that the structure will be permitted to be built with a lowest floor elevation below the base flood elevation and that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation. [Ord. 115 § 4, 1997]

16.12.070 Provisions for flood hazard reduction – General standards.

In all areas of special flood hazards, the following standards are required:

A. Anchoring.

1. All new construction and substantial improvements shall be anchored to prevent flotation, collapse or lateral movement of the structure.

2. All manufactured homes must likewise be anchored to prevent flotation, collapse or lateral movement, and shall be installed using methods and practices that minimize flood damage. Anchoring methods may include, but are not limited to, use of over-the-top or frame ties to ground anchors (Reference FEMA’s “Manufactured Home Installation in Flood Hazard Areas” guidebook for additional techniques).

B. Construction Materials and Methods.

1. All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage.

2. All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage.

3. Electrical, heating, ventilation, plumbing, and air conditioning equipment and other service facilities shall be designed and/or otherwise elevated or located so as to prevent water from entering or accumulating within the components during conditions of flooding.

C. Utilities.

1. All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the system;

2. New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharge from the systems into floodwaters; and

3. On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.

D. Subdivision Proposals.

1. All subdivision proposals shall be consistent with the need to minimize flood damage;

2. All subdivision proposals shall have public utilities and facilities such as sewer, gas, electrical and water systems located and constructed to minimize flood damage;

3. All subdivision proposals shall have adequate drainage provided to reduce exposure to flood damage; and

4. Where base flood elevation data has not been provided or is not available from another authoritative source, it shall be generated for subdivision proposals and other proposed developments which contain at least 50 lots or five acres (whichever is less).

E. Review of Building Permits. Where elevation data is not available either through the flood insurance study or from another authoritative source (SMC 16.12.060(C)(2)), applications for building permits shall be reviewed to assure that proposed construction will be reasonably safe from flooding. The test of reasonableness is a local judgment and includes use of historical data, high water marks, photographs of past flooding, etc., where available. Failure to elevate at least two feet above grade in these zones may result in higher insurance rates. [Ord. 115 § 5.1, 1997]

16.12.080 Provisions for flood hazard reduction – Specific standards.

In all areas of special flood hazards where base flood elevation data has been provided as set forth in SMC 16.12.050(B), Basis for Establishing the Areas of Special Flood Hazard, or SMC 16.12.060(C)(2), Use of Other Base Flood Data, the following provisions are required:

A. Residential Construction.

1. New construction and substantial improvement of any residential structure shall have the lowest floor, including basement, elevated one foot or more above the base flood elevation.

2. Fully enclosed areas below the lowest floor that are subject to flooding are prohibited, or shall be designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for the entry and exit of floodwaters. Designs for meeting this requirement must either be certified by a registered professional engineer or architect or must meet or exceed the following minimum criteria:

a. A minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding shall be provided;

b. The bottom of all openings shall be no higher than one foot above grade;

c. Openings may be equipped with screens, louvers or other coverings or devices; provided, that they permit the automatic entry and exit of floodwaters.

B. Nonresidential Construction. New construction and substantial improvement of any commercial, industrial or other residential structure shall either have the lowest floor, including basement, elevated to one foot or more above the level of the base flood elevation; or, together with attendant utility and sanitary facilities, shall:

1. Be floodproofed so that below one foot above the base flood level the structure is watertight with walls substantially impermeable to the passage of water;

2. Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy;

3. Be certified by a registered professional engineer or architect that the design and methods of construction are in accordance with accepted standards of practice for meeting provisions of this subsection based on their development and/or review of the structural design, specifications and plans. Such certifications shall be provided to the official as set forth in SMC 16.12.060(C)(3)(b);

4. Nonresidential structures that are elevated, not floodproofed, must meet the same standards for space below the lowest floor as described in subsection (A)(2) of this section;

5. Applicants floodproofing nonresidential buildings shall be notified that flood insurance premiums will be based on rates that are one foot below the floodproofed level (e.g., a building floodproofed at the base flood level will be rated as one foot below).

C. Manufactured Homes.

1. All manufactured homes to be placed or substantially improved within zones A1-A30, AH, and AE on the community’s FIRM on sites:

a. Outside of a manufactured home park or subdivision;

b. In a new manufactured home park or subdivision;

c. In an expansion to an existing manufactured home park or subdivision; or

d. In an existing manufactured home park or subdivision on which a manufactured home has incurred “substantial damage” as the result of a flood;

shall be elevated on a permanent foundation such that the lowest floor of the manufactured home is elevated one foot above the base flood elevation and be securely anchored to an adequately designed foundation system to resist flotation collapse and lateral movement.

2. Manufactured homes to be placed or substantially improved on sites in an existing manufactured home park or subdivision within zones A1-A30, AH, and AE on the community’s FIRM that are not subject to the above manufactured home provisions shall be elevated so that either:

a. The lowest floor of the manufactured home is elevated one foot above the base flood elevation; or

b. The manufactured home chassis is supported by reinforced piers or other foundation elements of at least equivalent strength that are no less than 36 inches in height above grade and be securely anchored to an adequately designed foundation system to resist flotation, collapse, and lateral movement.

D. Recreational Vehicles. Recreational vehicles placed on sites within zones A1-A30 AH, and AE on the community’s FIRM shall either:

1. Be on the site for fewer than 180 consecutive days;

2. Be fully licensed and ready for highway use, on its wheels or jacking system, is attached to the site only by quick disconnect type utilities and security devices, and has no permanently attached additions; or

3. Meet the requirements of subsection (B)(3) of this section and the elevation and anchoring requirements for manufactured homes. [Ord. 115 § 5.2, 1997]

16.12.090 Encroachments.

The cumulative effect of any proposed development, where combined with all other existing and anticipated development, shall not increase the water surface elevation of the base flood more than one foot at any point. [Ord. 115 § 5.3, 1997]

16.12.100 Critical facility.

Construction of new critical facilities shall be, to the extent possible, located outside the limits of the special flood hazard area (SFHA) (100-year floodplain). Construction of new critical facilities shall be permissible within the SFHA if no feasible alternative site is available. Critical facilities constructed within the SFHA shall have the lowest floor elevated three feet or more above the level of the base flood elevation (100-year) at the site. Floodproofing and sealing measures must be taken to ensure that toxic substances will not be displaced by or released into floodwaters. Access routes elevated to or above the level of the base flood elevation shall be provided to all critical facilities to the extent possible. [Ord. 115 § 5.4, 1997]