(1) The
office may enter into cost-reimbursement agreements with a
project proponent to recover from the project proponent the
reasonable costs incurred by the office in carrying out the
provisions of RCW 43.42.050, 43.42.060, 43.42.090, and 43.42.092.
The agreement must include the permit agencies that are
participating in the cost-reimbursement project and carrying out
permit processing tasks referenced in the agreement.
(2) The office must maintain policies or guidelines for
coordinating cost-reimbursement agreements with participating
agencies, project proponents, and outside independent
consultants. Policies or guidelines must ensure that, in
developing cost-reimbursement agreements, conflicts of interest
are eliminated. Contracts with independent consultants hired by
the office under this section must be based on competitive bids
that are awarded for each agreement from a prequalified
consultant roster.
(3) For fully coordinated permit processes, the office must
coordinate the negotiation of all cost-reimbursement agreements
executed under RCW 43.21A.690, 43.30.490, 43.70.630, 43.300.080,
and 70.94.085. The office, project proponent, and the permit
agencies must be signatories to the agreement or agreements.
Each permit agency must manage performance of its portion of the
agreement. Independent consultants hired under a
cost-reimbursement agreement shall report directly to the hiring
office or permit agency. Any cost-reimbursement agreement must
require that final decisions are made by the permit agency and
not by a hired consultant.
(4) For a fully coordinated project using cost
reimbursement, the office and participating permit agencies must
include a cost-reimbursement work plan, including deliverables
and schedules for invoicing and reimbursement in the fully
coordinated project work plan described in RCW 43.42.060. Upon
request, the office must verify that the agencies have met the
obligations contained in the cost-reimbursement work plan and
agreement. The cost-reimbursement agreement must identify the
tasks of each agency and the maximum costs for work conducted
under the agreement. The agreement must include a schedule that
states:
(a) The estimated number of weeks for initial review of the
permit application for comparable projects;
(b) The anticipated number of revision cycles;
(c) The estimated number of weeks for review of subsequent
revision submittals;
(d) The estimated number of billable hours of employee time;
(e) The rate per hour; and
(f) A process for revision of the agreement if necessary.
(5) If a permit agency or the project proponent foresees, at
any time, that it will be unable to meet its obligations under
the cost-reimbursement agreement and fully coordinated project
work plan, it must notify the office and state the reasons, along
with proposals for resolving the problems and potentially
amending the timelines. The office must notify the participating
permit agencies and the project proponent and, upon agreement of
all parties, adjust the schedule, or, if necessary, coordinate
revision of the cost-reimbursement agreement and fully
coordinated project work plan.
[2010 c 162 § 4; 2009 c 97 § 7; 2007 c 94 § 8; 2003 c 70 § 7; 2002 c 153 § 8.]
NOTES:
Effective date -- 2010 c 162: See note following RCW 43.42.090.