The department shall amend the state water quality
standards to authorize compliance schedules in excess of ten
years for discharge permits issued under this chapter that
implement allocations contained in a total maximum daily load
under certain circumstances. Any such amendment must be
submitted to the United States environmental protection agency
under the clean water act. Compliance schedules for the permits
may exceed ten years if the department determines that:
(1) The permittee is meeting its requirements under the
total maximum daily load as soon as possible;
(2) The actions proposed in the compliance schedule are
sufficient to achieve water quality standards as soon as
possible;
(3) A compliance schedule is appropriate; and
(4) The permittee is not able to meet its waste load
allocation solely by controlling and treating its own effluent.
[2009 c 457 § 1.]