(1) For applications to site
electrical transmission facilities, the council shall conduct a
preapplication process pursuant to rules adopted by the council
to govern such process, receive applications as prescribed in RCW 80.50.071, and conduct public meetings pursuant to RCW 80.50.090.
(2) The council shall consider and may recommend
certification of electrical transmission facilities in corridors
designated for this purpose by affected cities, towns, or
counties:
(a) Where the jurisdictions have identified electrical
transmission facility corridors as part of their land use plans
and zoning maps based on policies adopted in their plans;
(b) Where the proposed electrical transmission facility is
consistent with any adopted development regulations that govern
the siting of electrical transmission facilities in such
corridors; and
(c) Where contiguous jurisdictions and jurisdictions in
which related regional electrical transmission facilities are
located have either prior to or during the preapplication process
undertaken good faith efforts to coordinate the locations of
their corridors consistent with RCW 36.70A.100.
(3)(a) In the absence of a corridor designation in the
manner prescribed in subsection (2) of this section, the council
shall as part of the preapplication process require the
preapplicant to negotiate, as provided by rule adopted by the
council, for a reasonable time with affected cities, towns, and
counties to attempt to reach agreement about a corridor plan.
The application for certification shall identify only the
corridor agreed to by the applicant and cities, towns, and
counties within the proposed corridor pursuant to the
preapplication process.
(b) If no corridor plan is agreed to by the applicant and
cities, towns, and counties pursuant to (a) of this subsection,
the applicant shall propose a recommended corridor and electrical
transmission facilities to be included within the proposed
corridor.
(c) The council shall consider the applicant's proposed
corridor and electrical transmission facilities as provided in
RCW 80.50.090 (2) and (4), and shall make a recommendation
consistent with RCW 80.50.090 and 80.50.100.
[2007 c 325 § 3.]