(1) Contracts
for public improvements or work, other than for professional
services, by the state, or any county, city, town, district,
board, or other public body, herein referred to as "public body",
shall provide, and there shall be reserved by the public body
from the moneys earned by the contractor on estimates during the
progress of the improvement or work, a sum not to exceed five
percent, said sum to be retained by the state, county, city,
town, district, board, or other public body, as a trust fund for
the protection and payment of any person or persons, mechanic,
subcontractor or material supplier who shall perform any labor
upon such contract or the doing of said work, and all persons who
shall supply such person or persons or subcontractors with
provisions and supplies for the carrying on of such work, and the
state with respect to taxes imposed pursuant to Title 82 RCW
which may be due from such contractor. Every person performing
labor or furnishing supplies toward the completion of said
improvement or work shall have a lien upon said moneys so
reserved: PROVIDED, That such notice of the lien of such
claimant shall be given in the manner and within the time
provided in RCW 39.08.030 as now existing and in accordance with
any amendments that may hereafter be made thereto: PROVIDED
FURTHER, That the board, council, commission, trustees, officer
or body acting for the state, county or municipality or other
public body; (a) at any time after fifty percent of the original
contract work has been completed, if it finds that satisfactory
progress is being made, may make any of the partial payments
which would otherwise be subsequently made in full; but in no
event shall the amount to be retained be reduced to less than
five percent of the amount of the moneys earned by the
contractor: PROVIDED, That the contractor may request that
retainage be reduced to one hundred percent of the value of the
work remaining on the project; and (b) thirty days after
completion and acceptance of all contract work other than
landscaping, may release and pay in full the amounts retained
during the performance of the contract (other than continuing
retention of five percent of the moneys earned for landscaping)
subject to the provisions of RCW 60.28.020.
(2) The moneys reserved under the provisions of subsection
(1) of this section, at the option of the contractor, shall be:
(a) Retained in a fund by the public body until thirty days
following the final acceptance of said improvement or work as
completed;
(b) Deposited by the public body in an interest bearing
account in a bank, mutual savings bank, or savings and loan
association, not subject to withdrawal until after the final
acceptance of said improvement or work as completed, or until
agreed to by both parties: PROVIDED, That interest on such
account shall be paid to the contractor;
(c) Placed in escrow with a bank or trust company by the
public body until thirty days following the final acceptance of
said improvement or work as completed. When the moneys reserved
are to be placed in escrow, the public body shall issue a check
representing the sum of the moneys reserved payable to the bank
or trust company and the contractor jointly. Such check shall be
converted into bonds and securities chosen by the contractor and
approved by the public body and such bonds and securities shall
be held in escrow. Interest on such bonds and securities shall
be paid to the contractor as the said interest accrues.
(3) The contractor or subcontractor may withhold payment of
not more than five percent from the moneys earned by any
subcontractor or sub-subcontractor or supplier contracted with by
the contractor to provide labor, materials, or equipment to the
public project. Whenever the contractor or subcontractor
reserves funds earned by a subcontractor or sub-subcontractor or
supplier, the contractor or subcontractor shall pay interest to
the subcontractor or sub-subcontractor or supplier at a rate
equal to that received by the contractor or subcontractor from
reserved funds.
(4) With the consent of the public body the contractor may
submit a bond for all or any portion of the amount of funds
retained by the public body in a form acceptable to the public
body. Such bond and any proceeds therefrom shall be made subject
to all claims and liens and in the same manner and priority as
set forth for retained percentages in this chapter. The public
body shall release the bonded portion of the retained funds to
the contractor within thirty days of accepting the bond from the
contractor. Whenever a public body accepts a bond in lieu of
retained funds from a contractor, the contractor shall accept
like bonds from any subcontractors or suppliers from which the
contractor has retained funds. The contractor shall then release
the funds retained from the subcontractor or supplier to the
subcontractor or supplier within thirty days of accepting the
bond from the subcontractor or supplier.
(5) If the public body administering a contract, after a
substantial portion of the work has been completed, finds that an
unreasonable delay will occur in the completion of the remaining
portion of the contract for any reason not the result of a breach
thereof, it may, if the contractor agrees, delete from the
contract the remaining work and accept as final the improvement
at the stage of completion then attained and make payment in
proportion to the amount of the work accomplished and in such
case any amounts retained and accumulated under this section
shall be held for a period of thirty days following such
acceptance. In the event that the work shall have been
terminated before final completion as provided in this section,
the public body may thereafter enter into a new contract with the
same contractor to perform the remaining work or improvement for
an amount equal to or less than the cost of the remaining work as
was provided for in the original contract without advertisement
or bid. The provisions of this chapter 60.28 RCW shall be deemed
exclusive and shall supersede all provisions and regulations in
conflict herewith.
(6) Whenever the department of transportation has contracted
for the construction of two or more ferry vessels, thirty days
after completion and final acceptance of each ferry vessel, the
department may release and pay in full the amounts retained in
connection with the construction of such vessel subject to the
provisions of RCW 60.28.020: PROVIDED, That the department of
transportation may at its discretion condition the release of
funds retained in connection with the completed ferry upon the
contractor delivering a good and sufficient bond with two or more
sureties, or with a surety company, in the amount of the retained
funds to be released to the contractor, conditioned that no taxes
shall be certified or claims filed for work on such ferry after a
period of thirty days following final acceptance of such ferry;
and if such taxes are certified or claims filed, recovery may be
had on such bond by the department of revenue and the material
suppliers and laborers filing claims.
(7) Contracts on projects funded in whole or in part by
farmers home administration and subject to farmers home
administration regulations shall not be subject to subsections
(1) through (6) of this section.
[2007 c 218 § 91; 1986 c 181 § 6; 1984 c 146 § 1; 1982 c 170 § 1; 1981 c 260 § 14. Prior: 1977 ex.s. c 205 § 1; 1977 ex.s. c 166 § 5; 1975 1st ex.s. c 104 § 1; 1970 ex.s. c 38 § 1; 1969 ex.s. c 151 § 1; 1963 c 238 § 1; 1955 c 236 § 1; 1921 c 166 § 1; RRS § 10320.]
NOTES:
Intent -- Finding -- 2007 c 218: See note following RCW 1.08.130.
Application -- 1992 c 233: See RCW 39.04.901.
Severability -- 1977 ex.s. c 166: See note following RCW 39.08.030.