RCW 47.60.375
Capital plan.

(1) The capital plan must adhere to the following:

     (a) A current ridership demand forecast;

     (b) Vehicle level of service standards as described in RCW 47.06.140;

     (c) Operational strategies as described in RCW 47.60.327; and

     (d) Terminal design standards as described in RCW 47.60.365.

     (2) The capital plan must include the following:

     (a) A current vessel preservation plan;

     (b) A current systemwide vessel rebuild and replacement plan;

     (c) A current vessel deployment plan; and

     (d) A current terminal preservation plan.

[2008 c 124 § 3; 2007 c 512 § 13.]

NOTES:

     Finding -- Intent -- 2007 c 512: See note following RCW 47.06.140.