(1) Before approving
an agreement under subsection (2) of this section, the
commission, with the technical assistance of the department,
must:
(a) Prepare a financial analysis that fully discloses all
project costs, direct and indirect, including costs of any
financing;
(b) Publish notice and make available the contents of the
agreement, with the exception of patent information, at least
twenty days before the public hearing required in (c) of this
subsection; and
(c) Hold a public hearing on the proposed agreement, with
proper notice provided at least twenty days before the hearing.
The public hearing must be held within the boundaries of the
county seat of the county containing the project.
(2) The commission must allow at least twenty days from the
public hearing on the proposed agreement required under
subsection (1)(c) of this section before approving and executing
any agreements authorized under this chapter.
[2005 c 317 § 16.]