(1) Upon complaint by
an interested party, the director of labor and industries shall
cause an investigation to be made to determine whether there has
been compliance with this chapter and the rules adopted
hereunder, and if the investigation indicates that a violation
may have occurred, a hearing shall be held in accordance with
chapter 34.05 RCW. The director shall issue a written
determination including his or her findings after the hearing. A
judicial appeal from the director's determination may be taken in
accordance with chapter 34.05 RCW, with the prevailing party
entitled to recover reasonable costs and attorneys fees.
A complaint concerning nonpayment of the prevailing rate of
wage shall be filed with the department of labor and industries
no later than thirty days from the acceptance date of the public
works project. The failure to timely file such a complaint shall
not prohibit a claimant from pursuing a private right of action
against a contractor or subcontractor for unpaid prevailing
wages. The remedy provided by this section is not exclusive and
is concurrent with any other remedy provided by law.
(2) To the extent that a contractor or subcontractor has not
paid the prevailing rate of wage under a determination issued as
provided in subsection (1) of this section, the director shall
notify the agency awarding the public works contract of the
amount of the violation found, and the awarding agency shall
withhold, or in the case of a bond, the director shall proceed
against the bond in accordance with the applicable statute to
recover, such amount from the following sources in the following
order of priority until the total of such amount is withheld:
(a) The retainage or bond in lieu of retainage as provided
in RCW 60.28.011;
(b) If the claimant was employed by the contractor or
subcontractor on the public works project, the bond filed by the
contractor or subcontractor with the department of labor and
industries as provided in RCW 18.27.040 and 19.28.041;
(c) A surety bond, or at the contractor's or subcontractor's
option an escrow account, running to the director in the amount
of the violation found; and
(d) That portion of the progress payments which is properly
allocable to the contractor or subcontractor who is found to be
in violation of this chapter. Under no circumstances shall any
portion of the progress payments be withheld that are properly
allocable to a contractor, subcontractor, or supplier, that is
not found to be in violation of this chapter.
The amount withheld shall be released to the director to
distribute in accordance with the director's determination.
(3) A contractor or subcontractor that is found, in
accordance with subsection (1) of this section, to have violated
the requirement to pay the prevailing rate of wage shall be
subject to a civil penalty of not less than one thousand dollars
or an amount equal to twenty percent of the total prevailing wage
violation found on the contract, whichever is greater, and shall
not be permitted to bid, or have a bid considered, on any public
works contract until such civil penalty has been paid in full to
the director. If a contractor or subcontractor is found to have
participated in a violation of the requirement to pay the
prevailing rate of wage for a second time within a five-year
period, the contractor or subcontractor shall be subject to the
sanctions prescribed in this subsection and as an additional
sanction shall not be allowed to bid on any public works contract
for two years. Civil penalties shall be deposited in the public
works administration account. If a previous or subsequent
violation of a requirement to pay a prevailing rate of wage under
federal or other state law is found against the contractor or
subcontractor within five years from a violation under this
section, the contractor or subcontractor shall not be allowed to
bid on any public works contract for two years. A contractor or
subcontractor shall not be barred from bidding on any public
works contract if the contractor or subcontractor relied upon
written information from the department to pay a prevailing rate
of wage that is later determined to be in violation of this
chapter. The civil penalty and sanctions under this subsection
shall not apply to a violation determined by the director to be
an inadvertent filing or reporting error. To the extent that a
contractor or subcontractor has not paid the prevailing wage rate
under a determination issued as provided in subsection (1) of
this section, the unpaid wages shall constitute a lien against
the bonds and retainage as provided herein and in RCW 18.27.040,
19.28.041, 39.08.010, and 60.28.011.
[2009 c 219 § 4; 2001 c 219 § 2; 1994 c 88 § 1; 1985 c 15 § 2.]
NOTES:
Severability -- 1985 c 15: "If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected." [1985 c 15 § 4.]