(1) All subcontract
work and equipment and material purchases shall be competitively
bid with public bid openings. Subcontract bid packages and
equipment and materials purchases shall be awarded to the
responsible bidder submitting the lowest responsive bid. In
preparing subcontract bid packages, the general
contractor/construction manager shall not be required to violate
or waive terms of a collective bargaining agreement.
(2) All subcontract bid packages in which bidder eligibility
was not determined in advance shall include the specific
objective criteria that will be used by the general
contractor/construction manager and the public body to evaluate
bidder responsibility. If the lowest bidder submitting a
responsive bid is determined by the general
contractor/construction manager and the public body not to be
responsible, the general contractor/construction manager and the
public body must provide written documentation to that bidder
explaining their intent to reject the bidder as not responsible
and afford the bidder the opportunity to establish that it is a
responsible bidder. Responsibility shall be determined in
accordance with criteria listed in the bid documents. Protests
concerning bidder responsibility determination by the general
contractor/construction manager and the public body shall be in
accordance with subsection (4) of this section.
(3) All subcontractors who bid work over three hundred
thousand dollars shall post a bid bond. All subcontractors who
are awarded a contract over three hundred thousand dollars shall
provide a performance and payment bond for the contract amount.
All other subcontractors shall provide a performance and payment
bond if required by the general contractor/construction manager.
(4) If the general contractor/construction manager receives
a written protest from a subcontractor bidder or an equipment or
material supplier, the general contractor/construction manager
shall not execute a contract for the subcontract bid package or
equipment or material purchase order with anyone other than the
protesting bidder without first providing at least two full
business days' written notice to all bidders of the intent to
execute a contract for the subcontract bid package. The
protesting bidder must submit written notice of its protest no
later than two full business days following the bid opening.
Intermediate Saturdays, Sundays, and legal holidays are not
counted.
(5) A low bidder who claims error and fails to enter into a
contract is prohibited from bidding on the same project if a
second or subsequent call for bids is made for the project.
(6) The general contractor/construction manager may
negotiate with the lowest responsible and responsive bidder to
negotiate an adjustment to the lowest bid or proposal price based
upon agreed changes to the contract plans and specifications
under the following conditions:
(a) All responsive bids or proposal prices exceed the
available funds, as certified by an appropriate fiscal officer;
(b) The apparent low responsive bid or proposal does not
exceed the available funds by the greater of one hundred
twenty-five thousand dollars or two percent for projects valued
over ten million dollars; and
(c) The negotiated adjustment will bring the bid or proposal
price within the amount of available funds.
(7) If the negotiation is unsuccessful, the subcontract work
or equipment or material purchases must be rebid.
(8) The general contractor/construction manager must provide
a written explanation if all bids are rejected.
[2007 c 494 § 305.]
NOTES:
Sunset Act application: See note following chapter digest.