(1)
A public body using the general contractor/construction manager
contracting procedure shall provide for:
(a) The preparation of appropriate, complete, and
coordinated design documents;
(b) Confirmation that a constructability analysis of the
design documents has been performed prior to solicitation of a
subcontract bid package;
(c) Reasonable budget contingencies totaling not less than
five percent of the anticipated contract value;
(d) To the extent appropriate, on-site architectural or
engineering representatives during major construction or
installation phases;
(e) Employment of staff or consultants with expertise and
prior experience in the management of comparable projects,
critical path method schedule review and analysis, and the
administration, pricing, and negotiation of change orders;
(f) Contract documents that include alternative dispute
resolution procedures to be attempted before the initiation of
litigation;
(g) Contract documents that: (i) Obligate the public owner
to accept or reject a request for equitable adjustment, change
order, or claim within a specified time period but no later than
sixty calendar days after the receipt by the public body of
related documentation; and (ii) provide that if the public owner
does not respond in writing to a request for equitable
adjustment, change order, or claim within the specified time
period, the request is deemed denied;
(h) Submission of project information, as required by the
board; and
(i) Contract documents that require the contractor,
subcontractors, and designers to submit project information
required by the board.
(2) A public body using the general contractor/construction
manager contracting procedure may include an incentive clause for
early completion, cost savings, or other performance goals if
such incentives are identified in the request for proposals. No
incentives granted may exceed five percent of the maximum
allowable construction cost. No incentives may be paid from any
contingency fund established for coordination of the construction
documents or coordination of the work.
(3) If the construction is completed for less than the
maximum allowable construction cost, any savings not otherwise
negotiated as part of an incentive clause shall accrue to the
public body. If the construction is completed for more than the
maximum allowable construction cost, the additional cost is the
responsibility of the general contractor/construction manager.
(4) If the public body and the general
contractor/construction manager agree, in writing, on a price for
additional work, the public body must issue a change order within
thirty days of the written agreement. If the public body does
not issue a change order within the thirty days, interest shall
accrue on the dollar amount of the additional work satisfactorily
completed until a change order is issued. The public body shall
pay this interest at a rate of one percent per month.
[2007 c 494 § 302.]
NOTES:
Sunset Act application: See note following chapter digest.