RCW 39.10.320
Design-build procedure -- Project management
and contracting requirements.
(1) A public body utilizing the
design-build contracting procedure shall provide for:
(a) Reasonable budget contingencies totaling not less than
five percent of the anticipated contract value;
(b) Employment of staff or consultants with expertise and
prior experience in the management of comparable projects;
(c) Contract documents that include alternative dispute
resolution procedures to be attempted prior to the initiation of
litigation;
(d) Submission of project information, as required by the
board; and
(e) Contract documents that require the contractor,
subcontractors, and designers to submit project information
required by the board.
(2) A public body utilizing the design-build contracting
procedure may provide incentive payments to contractors for early
completion, cost savings, or other goals if such payments are
identified in the request for proposals.
[2007 c 494 § 203; 1994 c 132 § 7. Formerly RCW 39.10.070.]