RCW 39.10.300
Design-build procedure -- Uses.
(1) Subject to
the process in RCW 39.10.270 or 39.10.280, public bodies may
utilize the design-build procedure for public works projects in
which the total project cost is over ten million dollars and
where:
(a) The design and construction activities, technologies, or
schedule to be used are highly specialized and a design-build
approach is critical in developing the construction methodology
or implementing the proposed technology; or
(b) The project design is repetitive in nature and is an
incidental part of the installation or construction; or
(c) Regular interaction with and feedback from facilities
users and operators during design is not critical to an effective
facility design.
(2) Subject to the process in RCW 39.10.270 or 39.10.280,
public bodies may use the design-build procedure for parking
garages, regardless of cost.
(3) The design-build procedure also may be used for the
construction or erection of preengineered metal buildings or
prefabricated modular buildings, regardless of cost and is not
subject to approval by the committee.
(4) Except for utility projects, the design-build procedure
may not be used to procure operations and maintenance services
for a period longer than three years. State agency projects that
propose to use the design-build-operate-maintain procedure shall
submit cost estimates for the construction portion of the project
consistent with the office of financial management's capital
budget requirements. Operations and maintenance costs must be
shown separately and must not be included as part of the capital
budget request.
[2007 c 494 § 201. Prior: 2003 c 352 § 2; 2003 c 300 § 4; 2002 c 46 § 1; 2001 c 328 § 2. Formerly RCW 39.10.051.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date -- 2002 c 46: "This act is necessary for the immediate preservation of the public peace, health, or safety, or support of the state government and its existing public institutions, and takes effect immediately [March 14, 2002]." [2002 c 46 § 5.]
Effective date -- 2001 c 328: See note following RCW 39.10.210.